Aerospace Production Planning: The Complete Guide for Suppliers and MRO Shops

Guide · Step 8 of 10 · 62 min read · Updated · View the whole path · Deutsche Fassung

Header graphic: three key points of aerospace production planning.

As of November 20, 2026 · Based on industry and company data, IAQG/SAE standards, FAA and EASA regulations and the technical literature (see Sources)

Short answer: Aerospace production planning means matching customer rates with finite capacity, long lead times, certified special processes and complete traceability. Unlike high-volume industries, it is not enough to hit the date. You also have to prove how the part was made: every part needs a documented origin, a released configuration and a controlled process, and that evidence has to be planned just like machine hours.

Tuesday morning at a Tier 2 supplier of structural parts. The customer has raised next quarter's releases by a fifth because the aircraft maker is increasing its rate. The five-axis machining cells are already running three shifts. Heat treatment goes to an outside Nadcap-accredited processor with a three-week lead time. An engineering change has just arrived for two part numbers, which triggers a partial first article inspection. And since yesterday, the quality department has been searching for the material certificate of a titanium heat lot because a customer has a question about a lot that already shipped.

Each of these tasks can be solved on its own. The difficulty is that they all land in the same plan at the same time. That is what sets aerospace production planning apart from planning in many other industries: it plans not only quantities and dates but also evidence, approvals and configurations. And it does this in a market where the aircraft makers' order books are full for years while the supply chain is stuck in several places at once.

This guide is written for plant managers, planning and scheduling managers and quality managers at aerospace suppliers, and for planners at maintenance, repair and overhaul (MRO) shops and repair stations. Readers searching for aerospace production scheduling will find the scheduling side (finite capacity, APS, bottleneck control) in Sections 5, 10 and 11. The guide covers the market situation in 2026 with sourced numbers, what makes the industry different, the relevant standards and regulations on both sides of the Atlantic (FAA and EASA), traceability and genealogy, Wright learning curves with a worked example, how to plan a rate ramp-up, capacity planning with APS and simulation, MRO planning with unplanned findings, KPIs, a step-by-step approach and typical mistakes. A short introduction to the link between lead time and traceability is also available in the post Aerospace production planning: lead time and traceability on m365.fm.

A note on the European context: the original version of this guide was written for German suppliers, and much of the global supply chain for Airbus runs through Europe. Where European rules (EASA, EN standards) matter for US companies, for example when you supply European customers or hold dual FAA/EASA approvals, this guide explains them next to their US counterparts.

Key takeaways

Quick reading paths

You are …Read first
Plant manager at a supplier facing a rate increaseSections 1, 9 and 10 (market, learning curve, ramp-up with checklist)
Production planner or scheduler with unrealistic ERP plansSections 5, 6 and 11 (planning levels, lead time, APS and simulation)
Quality managerSections 3, 4 and 8 (standards and regulations, traceability, engineering changes)
MRO planner at a repair stationSections 3, 4 and 13 (Part 145, life-limited parts, MRO planning)
IT, digital or cybersecurity leadSections 3.6, 4, 11, 14 and 16 (ITAR/CMMC, data model, APS, digital twin, approach)

Table of contents

  1. The 2026 market: why planning has become the bottleneck
  2. What makes aerospace production planning different from other industries
  3. Standards and regulations that matter for planning
  4. Traceability and genealogy
  5. Planning levels: from customer rate to operation
  6. Understanding and reducing lead time
  7. Planning special processes and outside operations
  8. Engineering changes and configuration management
  9. Wright learning curves: theory and worked example
  10. Planning a rate ramp-up: calculation and checklist
  11. Capacity planning with APS, bottleneck management and simulation
  12. Supply chain risks 2022 to 2026 and what they mean for planning
  13. MRO planning: maintenance with unplanned findings
  14. Digital twin and digital thread
  15. KPIs for planning and control
  16. Approach: six steps to a reliable plan
  17. Common mistakes and how to avoid them
  18. iFAKT and aerospace
  19. Glossary
  20. FAQ: common questions about aerospace production planning
  21. Conclusion

1. The 2026 market: why planning has become the bottleneck

1.1 Record demand, limited delivery capacity

Commercial aviation is in an unusual situation: demand for new aircraft has never been higher, but the industry cannot deliver at the pace customers want. According to a study that the airline association IATA presented with Oliver Wyman in October 2025, the global backlog of commercial aircraft reached a record of more than 17,000 aircraft in 2024. Between 2010 and 2019 it averaged about 13,000 [9]. The study estimates that delivery delays cost airlines more than $11 billion in 2025. The largest items are excess fuel burn from older aircraft (about $4.2 billion), additional maintenance ($3.1 billion), engine leasing ($2.6 billion) and higher spare parts inventories ($1.4 billion) [9].

The numbers for the two large manufacturers show the picture in detail:

MetricAirbusBoeing
Deliveries 2025793 commercial aircraft, of which 607 A320 Family [2]600 commercial airplanes, of which 447 Boeing 737 [6]
Backlog8,754 at year-end 2025 [2]; 9,310 at the end of September 2026 [3]over 6,100 at year-end 2025, valued at about $567 billion [6]; over 6,300 at the end of September 2026, valued at $611.8 billion [47]
2026 targetaround 870 deliveries [3]no unit forecast in the sources cited
Status 2026547 deliveries through September 30 [3]; 621 through the end of October [5]161 deliveries in Q3 2026, of which 124 Boeing 737 [47]; 737 program still progressing toward stabilized production of 47 per month; 787 stable at 8 per month [47]

1.2 Rate targets and why they keep moving

For suppliers, the aircraft maker's monthly rate is the most important planning input, because it drives the releases through every tier of the supply chain. In its report on the first nine months of 2026, Airbus states these targets: 70 to 75 A320 Family aircraft per month by the end of 2027, then stabilizing at rate 75; rate 12 for the A350 in 2028; rate 13 for the A220 in 2028; and rate 5 for the A330 in 2029 [3].

The history of the "rate 75" target shows how volatile such assumptions are. Airbus originally wanted to reach this rate in 2025 to 2026. At the end of 2024 the target moved to 2027 [4]. In April 2026, Airbus CEO Guillaume Faury publicly blamed Pratt & Whitney for not delivering the number of engines ordered and spoke of shortfalls that matched neither demand nor orders [4]. Trade media consider a slip of rate 75 into 2028 possible [4]. The target range of 70 to 75 by the end of 2027 reflects the status of October 28, 2026 [3].

At Boeing, the FAA capped 737 MAX production at 38 airplanes per month after the door plug blowout on an Alaska Airlines flight in January 2024. In October 2025 the FAA approved an increase to 42 [7]. In May 2026, Boeing CEO Kelly Ortberg said the line was now running at rate 47; he described a further step to 52 as a bigger strain because of inventory levels in the supply chain [8]. Boeing's third-quarter release of October 27, 2026 describes the 737 program as still progressing toward stabilized production of 47 per month [47].

What this means for your planning: Rate targets are not commitments. They are planning assumptions with significant uncertainty. A supplier that builds capacity strictly to the official target risks idle cost. A supplier that builds too late becomes the bottleneck itself, in an industry where one missing part holds up an entire airplane. Robust planning therefore works with scenarios (for example rate 60, 67 and 75) and with investment triggers defined in advance.

1.3 The industry in numbers: United States and Germany

The US aerospace and defense industry is the largest in the world. According to the Aerospace Industries Association (AIA) and S&P Global Market Intelligence, the industry recorded total sales of $988.6 billion in 2025 (AIA puts total business activity at $1 trillion) and supported about 2.1 million jobs. About 1.1 million of those jobs and nearly $483 billion in activity are in the domestic supply chain. Exports reached $172.7 billion, up 25 % year over year [48]. In other words, roughly half of the jobs sit with suppliers, which is exactly the group this guide is written for.

Germany is a smaller but important part of the Airbus supply chain and the home market of the original version of this guide. The German Aerospace Industries Association (BDLI) reported record figures in May 2026: EUR 62 billion in revenue in 2025 (2024: EUR 52 billion, up 19 %) and 130,000 employees (previous year: 120,000). Civil aviation is the largest segment with EUR 45 billion in revenue (up 15 %), followed by military aviation with EUR 13.5 billion (up 35 %) and space with EUR 3.5 billion. The export share was 66 %, and research and development spending was about EUR 4 billion [1].

Behind these numbers, on both sides of the Atlantic, are many small and mid-sized suppliers next to the OEMs and large system houses. They make structural parts, cabin components, engine parts, systems and special processes, or provide maintenance services. For these companies in particular, the switch from underutilization (2020 to 2022) to sustained overload is a planning challenge.

1.4 The supplier view: what surveys show

The consulting firm Roland Berger surveyed 95 companies in the aerospace supply chain in early 2026 [10]. The results are revealing for anyone responsible for planning:

An earlier survey points in the same direction from a planning angle. In a rate readiness assessment of more than 100 suppliers in Asia, Europe and the US, the consultancy Vendigital found that 38 % had inadequate capacity planning processes. It named skills shortages, unknown condition of plant and machinery, lapsed maintenance programs and poor communication between senior planners and the shop floor as causes [55]. The article does not show a publication date; it refers to Airbus's 2021 plan to reach rate 75 by 2025, so the data is several years old.

The last point of the Roland Berger list is central for planning: special processes and inspections have themselves become bottlenecks in many supply chains. Section 7 covers how to deal with this.

2. What makes aerospace production planning different from other industries

Many planning principles apply to any discrete manufacturing. Aerospace, however, combines several characteristics that are familiar on their own but together require their own planning logic.

Hub showing four characteristics that set aerospace planning apart.

2.1 High mix, low volume and many variants

An aerospace supplier typically makes many part numbers in small quantities. Even at a rate of 75 aircraft per month, that is about 3.5 aircraft per working day (at about 21 working days per month). A part installed once per aircraft therefore has a daily quantity in the single digits. Add customer-specific variants (cabin configuration), spare parts demand and parts for older models. The result is a high-mix, low-volume (HMLV) environment in which setups, program changeovers and inspection effort tie up a large share of capacity.

2.2 Long lead times and deep bills of materials

A titanium structural part can spend many weeks between raw material and shipment: forging or casting, rough machining, heat treatment, finish machining, nondestructive testing (NDT), surface treatment, final inspection. Several of these steps often happen at outside specialists. The bills of materials of large assemblies are deeply nested; aircraft consist of millions of parts that come together across many supply tiers. The consequence: a delay at a lower tier often shows up weeks later on the final assembly line. If you do not understand and actively manage lead time, you are planning with buffers you do not know.

2.3 Certification, qualification and evidence

In aerospace it is not enough to make a part to dimension. It has to be made with a released process, on qualified equipment, by qualified people, from certified material and in the released configuration, and all of that has to be documented. This has direct planning consequences: an order cannot simply be moved to a machine that is free but not qualified. An employee without a valid qualification for a special process is not capacity from a planning point of view. A change of supplier can require a new first article inspection.

2.4 Rate logic instead of lot-size logic

Aircraft makers plan in monthly rates that are announced years ahead and raised step by step. A supplier has to translate this rate into its own production lots without losing its customer's cadence. At the same time, rate steps are rarely smooth: the customer builds inventory, pushes releases out or pulls them in. Good planning therefore separates the customer rate (what the customer needs in the long run) from the releases (what the customer orders in the short term) and tracks the gap.

2.5 Long product life cycles

An aircraft type is often built for decades and operated even longer. That means drawing revisions, material specifications and process approvals stay valid for a long time but keep changing. Spare parts for older configurations must remain available. And records have to be kept for very long periods. Under FAA rules, a production approval holder must keep quality records for at least 5 years for products and articles made under the approval and at least 10 years for critical components [41]; customer requirements often go further. In practice, retention periods follow from customer flow-downs and the applicable regulations.

2.6 The high cost of a mistake

A defective part that reaches the customer (an escape) can trigger rework on the final assembly line, inspections of delivered aircraft or, in extreme cases, groundings. The FAA treats this as a quality system topic in its own right: 14 CFR 21.137 lists "quality escapes" as one of the required elements of a production approval holder's quality system [41]. The Pratt & Whitney GTF engine shows what a material defect can lead to (Section 12). For planning this means: quality inspections are not a buffer you can cut when the schedule is tight. They are fixed parts of the routing.

3. Standards and regulations that matter for planning

3.1 The IAQG standards family at a glance

The International Aerospace Quality Group (IAQG) develops the industry's quality standards. They are published in the Americas as AS standards (by SAE International), in Europe as EN standards and in Asia as JISQ standards; the content is identical. The core standard is 9100, supplemented by standards for maintenance organizations (9110), distributors (9120), first article inspection (9102), variation management of key characteristics (9103) and others [13]. In the US you will mostly see the AS designations (AS9100D, AS9102C, AS9145); European customers and documents use EN 9100 and so on. They refer to the same requirements.

On the regulatory side, two systems matter for most suppliers: the US Federal Aviation Administration (FAA), whose rules are in Title 14 of the Code of Federal Regulations (14 CFR), and the European Union Aviation Safety Agency (EASA). Confusingly, both have a "Part 21" and a "Part 145", and in both systems Subpart G of Part 21 covers production approvals. The content is similar in purpose but not identical.

The following table summarizes what you need to know as a planning manager:

Standard / regulationContentPlanning impact
AS9100D (EN 9100:2018, JISQ 9100:2016)Quality management system for aviation, space and defense; includes ISO 9001:2015 plus about 105 industry-specific additional requirements, including configuration management, risk management, product safety, counterfeit parts prevention, traceability and on-time delivery [14][44]On-time delivery becomes an audited metric; traceability of material, processes, tools and people must travel with the order flow [14]
AS9102C (2023; EN 9102:2024)First article inspection (FAI): complete verification of the first part from the production process against all design characteristics [17][18][46]Plan FAI effort as its own operation; changes to design, material, source, process, tooling or location, and a production break of more than two years, trigger a full or partial FAI [18][34]
AS9103 / EN 9103:2023Variation management of key characteristics [19]Key characteristics require process capability studies and control charts; this ties up inspection capacity and affects lot sizes and inspection frequency
AS9145 (2016; EN 9145:2018)Advanced Product Quality Planning (APQP) and Production Part Approval Process (PPAP) for aerospace, five phases from planning to ongoing production [16][35][45]Production readiness must be demonstrated at customer rate (production readiness review, runs at rate); launch planning and proof of capacity become part of the approval [35]
AS9110 / EN 9110:2018Quality management system for aviation maintenance organizations [20]Adds quality system requirements to Part 145; relevant for planning processes, supplier control and KPIs in MRO
AS9120 / EN 9120Quality management system for distributors and stockists [13][14]Traceability and certificate chain for purchased standard parts and raw material
NadcapIndustry-managed accreditation program for special processes, founded in 1990 under SAE and administered by the Performance Review Institute (PRI); areas include heat treating, chemical processing, NDT, welding, coatings and composites [21][54]Many customers allow only accredited shops to perform special processes; this limits the choice of sources and often makes special processes the bottleneck
FAA 14 CFR Part 21, Subpart G (production certificate); also Subpart K (Parts Manufacturer Approval, PMA) and Subpart O (TSO authorization)Production approvals; 14 CFR 21.137 requires a written quality system with 14 elements, including design data control, supplier control, manufacturing process control, nonconforming product control, quality records and quality escapes [41]The approval holder controls its suppliers; records must be kept for at least 5 years (10 years for critical components) [41]. Most Tier 2 and Tier 3 suppliers hold no production approval themselves but work under their customer's supplier control
FAA 14 CFR Part 145Repair station certificate; work only within ratings and operations specifications, with current maintenance data, an FAA-approved training program and records kept for at least 2 years [42]Planning can only assign work the station is rated for, to trained staff, with current manuals and data at hand
EASA Part 21 Subpart GProduction Organisation Approval (POA) in the EU [22]The approval holder releases parts with an EASA Form 1 and oversees its suppliers; processes and staff must match the approval. Relevant for US suppliers to European customers
EASA Part 145Maintenance organization approval (Annex II to Regulation (EU) No 1321/2014) [23]Work only within the approved scope (rating), with certifying staff and valid maintenance data. A facility that holds both FAA and EASA approvals can issue a dual release on FAA Form 8130-3 [43]
EASA Part-CAMOContinuing airworthiness management organization, introduced by Regulation (EU) 2019/1383 [23]Plans the maintenance program, airworthiness directives and life-limited parts in Europe and hands work packages to the MRO
ITAR / EAR (USA)Export controls for defense articles (ITAR, 22 CFR 120–130) and dual-use items (EAR, 15 CFR 730–774) [36]Access to technical data and parts can be restricted by person and location; this also applies to planning and IT systems
DFARS / CMMC 2.0 (US defense programs)Cybersecurity Maturity Model Certification; DFARS clause 252.204-7021 effective November 10, 2025, phased in over three years; program rule 32 CFR Part 170 [49][50]Suppliers that process federal contract information (FCI) or controlled unclassified information (CUI) in their planning, ERP or MES systems need the required CMMC level; primes must check a subcontractor's CMMC status before award [49]
DFARS 252.225-7009 (specialty metals)Specialty metals, including titanium and titanium alloys, in items delivered under DoD contracts must be melted or produced in the US or a qualifying country; flows down to subcontracts for items containing specialty metals [51]Material planning must track melt origin by heat lot, not just alloy and quantity; a cheaper or faster lot from a non-qualifying source may not be usable

3.2 AS9100 in detail: what the standard means for planning

AS9100D adopts the structure of ISO 9001 and adds requirements that reach directly into planning [44]. Three of them are especially important.

Configuration management. You must know at any time which design revision applies to which order and which revision was actually built. This affects order release (release only valid revisions), the handling of open orders when changes come in and the documentation of deviations.

Traceability. The standard requires traceability of all raw materials, materials and processes used, as well as of tools and people [14]. For planning, this means every operation confirmation must at least record who worked, when, on which machine, with which material and to which process revision. Section 4 goes deeper.

On-time delivery. AS9100 names on-time delivery explicitly as a requirement [14]. Customers rate their suppliers on on-time delivery (OTD) and quality. Poor OTD is therefore not only a commercial issue but also an audit issue.

3.3 FAA production approval: what 14 CFR 21.137 means for planners

If you hold an FAA production certificate or a Parts Manufacturer Approval (PMA holders must meet the same quality system requirements under 14 CFR 21.307), or if you supply such a holder, the quality system requirements of 14 CFR 21.137 shape your planning [41]. The rule requires each applicant for or holder of a production certificate to establish a written quality system "that ensures that each product and article conforms to its approved design and is in a condition for safe operation" [41]. Its 14 elements read like a checklist for a planning process that works:

For a Tier 2 or Tier 3 supplier without its own approval, these requirements arrive as flow-downs in the customer's purchase order and supplier quality manual. The planning consequence is the same: the evidence has to be produced in the order flow, not reconstructed afterward.

3.4 Outlook: AS9100D becomes IA9100

The IAQG is working on a revision of 9100 that is to be published as IA9100. The new name is meant to unify the regional designations (AS, EN, JISQ). As of mid-October 2026, according to a review of the available information, there was no official publication and no confirmed date; estimates range from late 2026 to early 2027. The transition period for certificates has not been set either [15]. Until then, AS9100D (EN 9100:2018) remains the valid edition, and existing certificates remain valid [15]. Plan the transition as a separate project once the IAQG has published the standard, and agree the timing with your registrar.

3.5 AS9145: proving production readiness at customer rate

AS9145 brings APQP and PPAP, methods familiar from the automotive industry, to aerospace [45]. It structures the path to production in five phases: planning; product design and development; process design and development; product and process validation; and ongoing production, use and post-delivery service [35]. The PPAP package includes, among other things, design records, a process flow diagram, a process FMEA, a control plan, measurement system analysis, initial process capability studies and the first article inspection report (FAIR) [35].

Hub of the core standards that affect aerospace planning.

Phases 3 and 4 are decisive for planning. In phase 3, production readiness is assessed in a production readiness review, and the processes should meet requirements at the customer's demand rate. In phase 4, production runs must show that the process delivers conforming parts at customer rate [35]. In other words: proof of capacity is part of the approval. If your capacity exists only on paper, this is where it shows.

3.6 Defense programs: CMMC 2.0, export controls and specialty metals

Many aerospace suppliers serve both commercial and defense customers, often on the same machines and in the same ERP system. Three US requirements then reach into planning:

4. Traceability and genealogy

4.1 Why traceability is a planning task

Traceability is often treated as a pure quality topic. In reality it is created in the order flow, where work is planned, performed and confirmed. When a planner moves an order to a different machine, splits a lot or reroutes an outside operation, the part's genealogy changes. If that information is missing later, the part may in the worst case no longer be shippable because its record is incomplete.

A recent article in the German trade journal Produktion describes evidence and data quality as the real bottleneck for mid-sized suppliers to the defense industry. It cites a BearingPoint survey according to which only 10 % of the companies surveyed in Germany have a fully integrated data architecture, while 38 % work with fragmented systems [37]. The m365.fm podcast episode Traceability and Genealogy looks at how traceability and genealogy can be implemented technically and organizationally in manufacturing.

4.2 Terms: traceability, genealogy, as-designed and as-built

4.3 The data model: what you need to capture at a minimum

ObjectTypical attributesWhy planning needs it
Part / serial numberpart number, revision, serial number, configurationlink to customer order and design revision
Lot / batchlot number, quantity, splits and mergeslot sizing, scoping a recall
Raw materialmaterial, specification, heat, supplier, material certificate, melt origin (for DFARS specialty metals [51])release of material before the order starts
Operationmachine, NC program revision, tool, process parameters, start/endconfirmation, lead time, capacity reconciliation
Personnelemployee, qualification, validityassignment of qualified people only
Special processprocessor, accreditation, furnace load/tank number, certificateplanning of outside steps, containment of deviations
Inspectioninspection plan, gage, result, inspectorrelease, FAI, evidence for key characteristics
Deviationconcession, rework, deviation approvalas-built documentation, shippability
Release documentcertificate of conformity (C of C); at approved organizations FAA Form 8130-3 or EASA Form 1 [22][23][43]shipping release; suppliers without their own production approval usually ship to the approval holder with a certificate of conformity

A note on release documents for US readers: FAA Form 8130-3 (Authorized Release Certificate, Airworthiness Approval Tag) documents domestic airworthiness approvals, approvals for return to service and export approvals. It may only be issued by persons and organizations authorized by the FAA, and FAA Order 8130.21H states that suppliers without production approval may generally not issue it for parts shipped to their production approval holder; the order also notes that it is "not a delivery or shipping document" [43]. Facilities approved by both the FAA and EASA can issue a dual release on the 8130-3 that makes a part eligible for installation on US and EU aircraft [43]. The European counterpart for single EASA releases is the EASA Form 1 [22][23].

4.4 Life-limited parts

Certain parts, especially rotating engine parts such as disks and shafts, have an approved life in cycles or hours (life-limited parts, LLP). Their consumption must be documented without gaps over the entire life. In the US, owners and operators must keep records of "the current status of life-limited parts" for each airframe, engine, propeller, rotor and appliance, and these records are retained and transferred with the aircraft when it is sold [53]. In Europe, the same task is part of continuing airworthiness under EASA rules [23]. If part of the history is missing (so-called back-to-birth traceability), a technically perfect part can become unusable. For manufacturers this means: the part's birth record, meaning material, heat, forging lot and manufacturing data, must be complete. For MRO shops it means: without a complete history a part cannot be reinstalled, and planning has to source a replacement.

4.5 Counterfeit and unapproved parts

AS9100 explicitly requires measures to prevent counterfeit parts [14]. The FAA's Advisory Circular AC 21-29D (2016) describes how to detect and report suspected unapproved parts (SUP); it defines an unapproved part as one that fails to meet the criteria of 14 CFR 21.8 or 21.9, which includes intentionally misrepresented and counterfeit parts [52]. Its guidance for purchasing is directly relevant for planners: buy from sources whose documentation traces parts back to an FAA-approved source, and be wary of warning signs such as a price far below other sellers, an unusually short delivery time or missing documentation [52]. Suspected unapproved parts are reported on FAA Form 8120-11 [52].

For planning this means: purchases may only come from approved sources, certificates must be checked at receiving inspection, and a quickly sourced replacement from an unknown source is not an option, not even under schedule pressure. Supply shortages raise the risk, because the pressure to turn to gray-market sources increases.

4.6 In practice: building traceability into the planning process

  1. Reserve and release material before the order starts. An order starts only when the specific material (heat lot, certificate) is assigned and checked.
  2. Model qualifications in the capacity model. Planning assigns operations only to people and machines with valid qualifications.
  3. Capture splits and merges in the system. Every lot split creates a new lot number linked to its origin.
  4. Plan outside operations including the return of certificates. A part is only back when its certificate is back.
  5. Record confirmations at the workstation, not at the end of the shift. The later you record, the more is missing.
  6. Test your queries regularly. Run a mock recall: how long does it take to find all serial numbers for a heat lot?

5. Planning levels: from customer rate to operation

5.1 Four levels, four time horizons

Aerospace production planning can be divided into four levels. Each answers a different question and needs different data.

LevelHorizonKey questionTypical tools
Strategic rate and capacity planning2 to 5 yearsWhich rate can we deliver with which investment?scenario calculation, factory simulation, capital planning
Sales and operations planning (S&OP) and master production scheduling6 to 24 monthsHow do we translate customer rates into a feasible program?ERP, rough-cut capacity planning, APS
Material and capacity planning1 to 6 monthsWhich material and which capacity do we need when?ERP/MRP, supplier portals, APS
Detailed scheduling and shop floor controlhours to 4 weeksWhich order runs when, on which machine, with whom?APS, MES, shop floor board

A common cause of poor on-time delivery is not one weak level but a break between levels: the master schedule commits to rate 75, the detailed schedule knows the bottlenecks that make this impossible, and nobody reconciles the two systematically.

5.2 ERP, APS and MES: who does what

In most companies, enterprise resource planning (ERP) is the leading system for orders, bills of materials, routings, inventory and purchasing. Its classic material requirements planning (MRP), in its basic form, calculates with fixed planned lead times and without capacity limits. That is enough to determine material requirements, but not to create a feasible production schedule.

A system for advanced planning and scheduling (APS), by contrast, schedules against finite capacity: machines, people with qualifications, tools, shifts and material availability are considered at the same time. The underlying method is called constraint-based scheduling. Finally, a manufacturing execution system (MES) controls and documents execution on the shop floor and provides the confirmations without which neither planning nor traceability works.

The sister guide Production scheduling and APS covers the differences between ERP, APS and MES, the limits of MRP logic and how to select planning software in detail.

5.3 What an aerospace planning model has to capture in addition

Compared with generic manufacturing, a planning model in aerospace needs some additional constraints:

6. Understanding and reducing lead time

In 1961, John D. C. Little proved a relationship that holds for every stable production system: the average inventory in the system equals throughput multiplied by the average time in the system [27]. Rearranged:

Lead time = work in process (WIP) ÷ throughput

Worked example: A shop for engine components ships an average of 40 parts per week. There are 320 parts in the system (being processed, waiting, at the outside processor, in inspection). The average lead time is then 320 ÷ 40 = 8 weeks. If WIP can be reduced to 200 parts at the same throughput, lead time drops to 5 weeks. Throughput does not change as long as the bottleneck stays fully supplied.

Four steps from material release to documented shipment.

The law explains why releasing more orders to the shop floor does not shorten delivery time but lengthens it: WIP rises, throughput stays the same, lead time grows.

6.2 Where the time goes

In many factories, actual processing time is only a small part of lead time; the larger part is waiting time. This is a widely shared rule of thumb, not a generally documented ratio unverified. The share depends heavily on the company and should be measured in your own plant, for example with value stream mapping. In aerospace, typical causes are:

6.3 Levers for shorter lead times

  1. Limit WIP. Release only as many orders as the bottleneck can process. The Theory of Constraints calls this the "rope" (Section 11).
  2. Bundle and schedule outside steps. Fixed pickup and delivery days with the processor reduce variability.
  3. Plan inspection capacity. The inspection lab and inspectors are capacity just like machines and belong in the capacity plan.
  4. Clear documents before the start. No order without complete documents, material with certificate and a valid design revision.
  5. Do not load bottlenecks above 85 to 90 % for long periods when variability is high. This rule of thumb follows from queueing theory (Section 11.1); the right value depends on the variability in your plant. A small capacity reserve often costs less than long queues.

7. Planning special processes and outside operations

7.1 Why special processes often become the bottleneck

Special processes are processes whose result cannot be fully verified on the finished part without destroying it, for example heat treating, surface treatment, welding or certain coatings. Their quality must therefore be ensured through qualified processes, equipment and people. In aerospace, many customers require Nadcap accreditation for them [21][54].

This has three consequences for planning. First, the number of approved sources is limited; a change requires qualification and often a new first article inspection. Second, many of these processes run in batches (furnaces, tanks, autoclaves), which creates batching and waiting times. Third, suppliers report that testing and surface treatment in particular have long lead times [10].

7.2 Planning rules for special processes

7.3 In-house special processes: make or buy from a capacity point of view

Many suppliers consider bringing special processes in-house to reduce their dependency. This can make sense, but it is a project with a long lead time of its own: equipment, qualification, accreditation, staff and customer approvals. A simulation of future utilization (Section 11.4) helps to clarify whether the investment pays off or whether the in-house equipment only creates a new bottleneck with low utilization.

8. Engineering changes and configuration management

8.1 Changes are normal in aerospace

Over the long life of an aircraft program, drawings, materials, processes and suppliers change again and again. Every change has to be assessed, approved and given an effectivity: from which serial number, aircraft or date does the new revision apply? For planning, this is a permanent source of disruption.

8.2 What a change triggers in planning

ImpactPlanning consequence
New design revisionreview open orders: let them run out, rework, scrap or ship with a concession
New or changed operationsupdate routing, standard times, NC programs and inspection plans
First article inspection (full or partial)schedule FAI as its own operation with inspection capacity; approval before production deliveries [18][34]
Change of material or supplierqualification, possibly a new FAI, new certificates and procurement lead times
New tooling or fixturesprocurement lead time, acceptance, possibly FAI for changed tooling

Under AS9102, a design change affecting form, fit or function, a change of manufacturing source, process, location or tooling, and a production break of more than two years, among other things, trigger a full or partial first article inspection [34]. Revision C of AS9102, published in 2023, puts more emphasis on the planning, evaluation and repetition of first article inspections [18][46]. In Europe, the corresponding edition was published as EN 9102:2024 (in Germany as DIN EN 9102:2025-01) [17].

8.3 Practical rules for handling changes

  1. Bundle changes where the customer allows it. Many small individual changes cost more than a few bundled ones.
  2. Set effectivity early and transfer it to planning. An order must know at its start which revision it is building.
  3. Actively manage inventory of old revisions. Launching large lots of the old revision when a change is foreseeable produces scrap.
  4. Reserve FAI capacity. Inspection resources for first articles are quickly overloaded during ramp-ups and waves of changes.
  5. Make change status visible on the planning board. Orders with open changes are risk orders.

9. Wright learning curves: theory and worked example

9.1 The 1936 discovery

In 1936, Theodore Paul Wright published the paper "Factors Affecting the Cost of Airplanes" in the Journal of the Aeronautical Sciences (vol. 3, no. 4, pp. 122–128) [24]. He found that the labor hours needed per airplane fell by about 20 % with every doubling of cumulative production [25]. This pattern is known today as Wright's Law or the learning curve. A 20 % reduction per doubling is called an 80 % learning curve; the name states the remaining share [25].

Learning curves are still a standard tool for cost estimating and capacity planning in aerospace. The US Government Accountability Office (GAO) describes them in its Cost Estimating and Assessment Guide [26].

9.2 Two variants: cumulative average and unit model

There are two common formulations [26]:

Both use the same formula but different reference quantities [26][40]. Decide which variant you use and stick with it. If you transfer a learning rate from the cumulative average model to the unit model, you compare actual and target values that do not match.

The formula is: Y = A · X^b, where A = hours for the first unit, X = cumulative units and b = log(learning rate) ÷ log(2) [26].

9.3 Worked example: launching a new assembly

A supplier takes over the assembly of a new subassembly. The first unit requires 1,000 assembly hours. Based on comparable programs, an 85 % learning curve is assumed (cumulative average model).

Step 1: Calculate the exponent. b = log(0.85) ÷ log(2) = −0.2345.

Step 2: Average and unit hours. The hours for unit N follow from the difference of the cumulative totals: T(N) = N · avg(N) − (N−1) · avg(N−1).

Cumulative units NAverage hours per unitCumulative hoursHours for unit N
11,000.01,0001,000.0
2850.01,700700.0
4722.52,890571.3
8614.14,913477.4
16522.08,352402.6
32443.714,199340.9
50399.619,981306.6
100339.733,968260.3

Step 3: What this means for capacity planning. If the supplier planned the first ten units with the hours of the hundredth unit (260 hours), it would arrive at 2,603 hours. According to the learning curve, the first ten units actually need 5,828 hours, more than twice as much. A launch planned with mature-rate standard hours is therefore systematically underplanned.

Step 4: Check sensitivity. How strongly does the result depend on the assumed learning rate? With a 90 % curve instead of 85 %, the requirement for the first 100 units rises from 33,968 to 49,659 hours, an increase of 46 %. The choice of learning rate is thus one of the most consequential assumptions in the entire launch plan.

9.4 Practical rules for learning curves

10. Planning a rate ramp-up: calculation and checklist

10.1 Why ramp-ups fail at the bottleneck

A rate increase is often assessed on the basis of total capacity: "We are at 75 % utilization on average, so we can handle 20 % more." That is rarely true, because throughput is determined by the bottleneck, not by the average. Eliyahu M. Goldratt's Theory of Constraints made this principle popular in the 1980s [28].

Ladder of hours per unit for an 85 percent learning curve.

10.2 Worked example: rate 60 to rate 72

A supplier delivers one set of fitting parts per aircraft. The customer rate is to rise from 60 to 72 aircraft per month (up 20 %). The three most important resources look like this:

ResourceAvailable hours/monthLoad at rate 60Utilization rate 60Load at rate 72Utilization rate 72
5-axis machining1,4001,19085 %1,428102 %
Deburring and assembly2,0001,30065 %1,56078 %
Inspection lab (CMM)60042070 %50484 %
Total (hours-weighted)4,0002,91073 %3,49287 %

Total utilization of 87 % sounds feasible. But 5-axis machining, at 102 %, is above its capacity, and that is without accounting for disruptions, setups for additional variants or first article inspections after changes. On top of that comes the effect from Section 6: the closer utilization gets to 100 %, the more the queues grow. Without action, lead time and late deliveries increase even though total capacity is mathematically sufficient.

Possible actions, ordered by lead time:

  1. Immediately: protect the bottleneck (no idle time during breaks, prepare setups outside machine time, decouple inspection from the machine).
  2. Weeks: extra weekend shifts, move parts with lower complexity to other qualified machines.
  3. Months: program optimization (cycle time), fixtures for multiple setups, outsourcing individual parts to qualified partners (with FAI).
  4. Quarters to years: an additional machine including delivery time, installation, qualification and customer approval.

The last point shows why ramp-ups in aerospace need so much lead time: between the decision for a new machine and its first approved production delivery there are often many months.

10.3 Checklist: is your plant ready for the next rate?

Demand and scenarios

Capacity

People

Material and suppliers

Quality and approvals

Control

11. Capacity planning with APS, bottleneck management and simulation

11.1 Why high utilization costs time

Queueing theory provides a simple rule of thumb: the average waiting time at a resource grows with the factor u ÷ (1 − u), where u is utilization. This approximation goes back to J. F. C. Kingman (1961); in its full form it also includes the variability of arrivals and processing times [38]. At 80 % utilization the factor is 4, at 90 % it is already 9 and at 95 % it is 19. Waiting time at a resource with 95 % utilization is therefore almost five times as long as at 80 %, all else being equal.

This is especially relevant for aerospace with its high variability (changes, rework, outside processes, rush orders). If you plan a bottleneck at 98 % utilization, you are planning long lead times along with it.

11.2 Bottleneck management with the Theory of Constraints

The Theory of Constraints (TOC) describes five focusing steps: identify the constraint, exploit it, subordinate everything else to it, elevate it, and then start again, because the constraint moves [28]. For shop floor control, the drum-buffer-rope (DBR) principle has become established:

In aerospace, the bottleneck is often not in your own building but at the outside special process or in the inspection lab. DBR still works if you treat the outside step as the drum and tie your own release to its slots.

11.3 APS in aerospace: what it has to do

An APS system for an aerospace supplier should be able to do at least the following:

CapabilityWhy it matters in aerospace
Scheduling against finite capacityBottlenecks are the rule, not the exception
Qualifications of people and machinesOnly qualified resources may be scheduled
Outside operations with slotsSpecial processes are often the real bottleneck
Batch buildingFurnaces, tanks and autoclaves work in batches
Inspection and release stepsFAI and inspections tie up capacity
Fast reschedulingChanges, rework and rush orders are frequent
Scenarios (what-if)Evaluate rate scenarios, investments, supplier failures
Feedback from the shop floorWithout actual data, every plan goes stale
Integration with ERP and MESMaster data and orders come from ERP, actual data from MES
Access control for controlled dataITAR and CUI orders must be visible only to authorized users [36][49]

The sister guide Production scheduling and APS contains a selection checklist and an implementation roadmap for APS systems.

11.4 Simulation: test capacity decisions before you make them

A factory simulation represents resources, orders, variability and rules in a model and plays through weeks or months in minutes. It answers questions that a static capacity calculation cannot:

Simulation does not replace detailed scheduling; it prepares strategic and tactical decisions. It is especially valuable before investments with long lead times, which is exactly the situation many suppliers are in with the current rate plans. On m365.fm you will also find the entity page Philip Schubert on the topic of planning and simulation.

Comparison of planning by average utilization and by bottleneck.

12. Supply chain risks 2022 to 2026 and what they mean for planning

12.1 What happened in recent years

Engines. In 2023, Pratt & Whitney disclosed a defect in the powder metal of certain parts of the geared turbofan (GTF) engine that can lead to cracks. In September 2023, parent company RTX announced that an additional 600 to 700 engines would have to be removed for shop visits through 2026 and expected an average of 350 A320 Family aircraft per year to be grounded. RTX took a pre-tax charge of $3 billion; total costs were estimated at up to $7 billion, part of which falls on partners such as MTU [11]. In 2026, Airbus accused Pratt & Whitney of prioritizing maintenance in the field over new engines and of not delivering the quantities ordered [4]. By mid-2026, Airbus said it no longer had finished aircraft waiting only for engines, but it had no buffer either [39].

Titanium. After Russia's attack on Ukraine, Boeing suspended purchases from the Russian titanium producer VSMPO-Avisma in March 2022. Airbus, which at the time said it sourced about half of its titanium from Russia, initially continued buying [12]. Titanium remains one of the most frequently cited raw material risks in 2026 [10]. For suppliers on US defense programs, the DFARS specialty metals clause adds a source restriction on top of the availability problem [51].

Castings and forgings. Roland Berger reports persistent gaps in 2026 for castings and forgings for engine and system components (such as landing gear) and for fasteners for structures. For turbine blades, aerospace competes with industrial gas turbines, whose demand is also rising because of the power needs of data centers [10].

Skilled labor. The shortage of qualified staff remains the most common brake on the ramp-up (56 % of respondents) [10]. The situation in maintenance is similar (Section 13).

Structural change among suppliers. Airbus is taking over former Spirit AeroSystems work packages. The integration reduced Airbus's results for the first nine months of 2026 by EUR 235 million [3]. Shifts like this change supply relationships on all tiers below.

12.2 Planning responses

RiskPlanning response
Long and variable material lead timeslong-term agreements with capacity commitments, safety stock targeted at critical materials, update replenishment lead times regularly
Single sources for special processesqualify second sources, secure slots by contract, model the bottleneck in the plan
Fluctuating customer releasestrack customer rate and releases separately, raise deviations early
Labor shortagequalification matrix, cross-training, onboarding in the capacity plan
Supplier failuresimulate scenarios, watch early warning indicators (late deliveries, quality, financial health)
Inventory build-up against disruptionshold inventory deliberately and in limited amounts where it protects the bottleneck; every unit of inventory lengthens lead time according to Little's Law

An important note on the last point: inventory is not free protection. According to Roland Berger, 40 % of suppliers built up higher inventories for the start of production, which puts pressure on their already thin margins [10]. Targeted buffers in front of the bottleneck are more effective than blanket safety stock across all parts.

13. MRO planning: maintenance with unplanned findings

13.1 The MRO market in 2026

Maintenance, repair and overhaul (MRO) is a large and growing market. In its forecast published with the US Aeronautical Repair Station Association (ARSA), Oliver Wyman puts the global commercial aviation MRO market at $139.6 billion for 2026 and expects it to grow to $193.1 billion by 2036. Engine maintenance is the largest segment at $70.1 billion. The fleet is expected to grow from about 30,000 commercial aircraft at the start of 2026 to about 41,100 in 2036 [30]. In a separate analysis from September 2026, Oliver Wyman points to material shortages, long lead times for castings and forgings and few suppliers for critical engine parts; almost 30 % of respondents expect the supply chain to fully recover only in more than three years [29].

Delayed new aircraft deliveries add to the pressure: airlines operate older aircraft longer, and these need more maintenance. The IATA study estimates the additional maintenance cost in 2025 alone at $3.1 billion [9]. At the same time, new production and maintenance compete for the same parts and capacity, as the dispute between Airbus and Pratt & Whitney shows [4].

13.2 Regulatory framework

In the US, a maintenance shop typically works under a repair station certificate issued under 14 CFR Part 145. A repair station may only work on articles for which it is rated and within its operations specifications, and it "may not maintain or alter any article for which it is not rated" [42]. It must keep current maintenance data such as airworthiness directives, maintenance manuals, overhaul manuals and service bulletins "current and accessible when the relevant work is being done", run an FAA-approved training program, and keep records of work for at least two years from approval for return to service [42]. Work packages typically come from the aircraft operator, which is also responsible for records such as the current status of life-limited parts under 14 CFR 91.417 [53]. Many repair stations are also certified to AS9110 [20].

In Europe, a maintenance organization works with an approval under EASA Part 145. The work packages often come from a continuing airworthiness management organization (Part-CAMO), which manages the maintenance program, airworthiness directives and life-limited parts [23]. US repair stations that also hold EASA approval can issue dual releases on FAA Form 8130-3 [43].

For planning, both systems mean the same thing: work is only allowed within the approved scope, by authorized staff and to valid maintenance data, such as the Aircraft Maintenance Manual (AMM) or the Component Maintenance Manual (CMM) in its current revision. A technician without the right authorization or training is not capacity here either.

13.3 What makes MRO planning fundamentally different

In new production, the work content is known before the order starts. In maintenance, it is only known after the aircraft, engine or component has been opened and inspected. Planning therefore has to deal with three types of work:

The central KPI is turnaround time (TAT), the time from induction to return to the customer. Every day an aircraft or engine spends longer in the shop costs the operator money. TAT is often determined less by labor hours than by waiting for parts, decisions on findings, approvals and specialists.

13.4 Worked example: plan findings instead of hoping

A component MRO shop plans the overhaul of one component type. Routine work is 80 hours. From the shop's own history of the last 50 orders, there are three typical findings (all values are assumptions for the example):

FindingFrequencyAdditional hoursParts required
Corrosion, repairable40 %12 hno
Crack, part replacement10 %20 hyes, lead time 15 working days, no stock
Wear, replacement part30 %6 hyes, from stock

Expected additional hours: 0.4 × 12 + 0.1 × 20 + 0.3 × 6 = 4.8 + 2.0 + 1.8 = 8.6 hours. On average, about 89 hours per order can be planned. For capacity planning across many orders, this expected value is useful.

For the TAT commitment, it is not enough. For 10 % of orders, 15 working days of waiting for the replacement part are added. If you commit to TAT as an average (mathematically a 1.5-day allowance), you will miss it badly on every tenth order. Better options are:

  1. Stock the part: one or two parts in stock greatly reduce the TAT risk. Compare the cost of inventory with the cost of delay.
  2. Inspect earlier: the sooner the finding is known, the sooner you can order. Schedule inspection as the first step with priority.
  3. Commit TAT by percentile: for example a TAT that is met in 80 or 90 % of cases, with a transparent rule for findings with long parts lead times.
  4. Exchange pool: for frequent findings, a rotable exchange pool can decouple TAT from the repair cycle.

13.5 Practical rules for MRO planning

14. Digital twin and digital thread

14.1 Terms

A digital twin of production is a model of the real factory that is fed with current data and used for analysis, planning and simulation. It covers resources, orders, routings, inventory and rules. The digital thread is the continuous link of a product's data across its life cycle: from design through manufacturing and inspection to operation and maintenance. In aerospace, the digital thread is closely tied to traceability and configuration management, because it connects as-designed, as-built and as-maintained.

Four steps for planning outside special processes.

14.2 Benefits for planning and quality

14.3 Prerequisites

A digital twin is only as good as its data. Before you invest in models, check routings, standard times, capacity calendars, qualifications and confirmation quality. The consultancy 4flow names incorrect bills of materials, outdated lead times and data scattered across disconnected ERP, PLM and MES platforms as typical obstacles in aerospace, which often push planners back to disconnected spreadsheets [33]. The sister guide Digital twin in manufacturing covers this topic in more depth; IT architecture questions, such as connecting machine and planning data to cloud platforms, are covered in the guide Manufacturing IT with Azure. For data subject to export controls or CUI rules, storage location and access rights must be clarified up front [36][37][49]. In US defense programs this includes the CMMC level required for the systems that hold the data [49][50].

15. KPIs for planning and control

KPIDefinitionWhy it matters in aerospace
On-time delivery (OTD)share of deliveries on the committed date (agree definition and tolerance window with the customer)central criterion of supplier ratings; named as a requirement in AS9100 [14]
Lead timetime from order start to completion, as average and spreaddetermines delivery capability and inventory (Little's Law) [27]
Work in process (WIP)number or value of orders on the shop floorleading indicator of rising lead times
Bottleneck utilizationoccupied time ÷ available time at the bottleneckdetermines throughput; above 90 % waiting times rise sharply [38]
Schedule adherenceshare of operations completed in the planned time windowshows whether the plan is realistic
Escapesnumber of defective parts reaching the customerhighest cost impact, often a customer metric; a required quality system element for FAA production approval holders [41]
First pass yield (FPY)share of parts without rework or scraprework consumes bottleneck capacity
FAI lead timetime from completion of the first article to approvalfrequently underestimated factor in ramp-ups and changes
Learning curve deviationactual hours per unit versus target curveshows whether launch assumptions hold
Turnaround time (TAT)time from induction to return in MRO, as average and percentilemain criterion for MRO customers
Finding rateshare of orders with non-routine work and its effortbasis of MRO capacity planning

A note on measurement: Define each KPI unambiguously and apply the definition consistently. OTD definitions in particular differ between customers (reference to first requested or confirmed date, allowed early delivery, partial or complete delivery). A metric that everyone calculates differently controls nothing. The sister guide Manufacturing KPIs covers KPI definitions in more detail.

16. Approach: six steps to a reliable plan

Step 1: Measure the current state. Capture lead times, WIP, OTD and utilization by resource over at least three months. A value stream map for the most important part families shows where time is lost.

Step 2: Identify bottlenecks. Where do orders pile up? Which resource determines throughput? Include outside special processes, inspection and staff qualifications.

Step 3: Clean up master data. Routings, standard times, setup times, capacity calendars, qualifications, replenishment lead times. Without this basis, every planning tool produces wrong results.

Step 4: Introduce control rules. Limit WIP, tie release to the bottleneck, protect the bottleneck with a buffer and set priority rules.

Step 5: Introduce constraint-based scheduling. Add detailed scheduling to the ERP that considers finite capacity, qualifications and outside slots. Start with a pilot area, ideally at the bottleneck.

Step 6: Establish scenarios and a feedback loop. Use simulation for rate and investment decisions and reconcile plan and actuals weekly. Keep improving planning parameters based on the confirmations.

Quick check for plant and planning managers: five questions you can answer this week

  1. Which resource is your bottleneck today, and what was its utilization over the last four weeks?
  2. How many orders are on the shop floor right now, and how many of them are waiting for outside special processes or inspection?
  3. How long does it take to find all serial numbers for a specific raw material heat lot?
  4. Which standard times are you using for parts that are just launching: mature-rate times or a learning curve?
  5. What happens to your on-time delivery if your most important outside processor is down for two weeks?

If you cannot answer one of these questions with data within a day, start with Step 1.

Timeline: Steps 1 to 4 require no new software and, in the author's experience, can be implemented in many companies within a few months unverified. Steps 5 and 6 require a software implementation; their duration depends mainly on master data quality. Reliable industry figures on duration are not available.

17. Common mistakes and how to avoid them

  1. Planning with infinite capacity. The MRP logic in ERP ignores bottlenecks. Result: plans that are infeasible from the start. Fix: detailed scheduling against finite capacity.
  2. Releasing more orders to deliver faster. According to Little's Law, higher WIP lengthens lead time. Fix: tie release to the bottleneck.
  3. Modeling outside special processes as a fixed lead time. Outside processes have capacities, cadences and variability. Fix: agree slots and plan them as a resource.
  4. Forgetting inspection and FAI. The inspection lab and inspectors are not planned and become a hidden bottleneck. Fix: inspection steps as operations with capacity.
  5. Using mature-rate standard times during launch. Learning curves are ignored, the launch is underplanned. Fix: learning curve from your own data.
  6. Assessing the average instead of the bottleneck. An average utilization of 75 % says nothing about the bottleneck resource. Fix: assess resource by resource, focus on the bottleneck.
  7. Reconstructing traceability after the fact. Missing confirmations are pieced together at the end. Fix: capture in the process, assign material before the start.
  8. Ignoring qualifications. The plan assigns tasks to people without valid qualifications. Fix: qualification matrix as a constraint.
  9. Treating rate targets as commitments. Capacity is built to an official target that then slips. Fix: scenarios with triggers.
  10. Committing to the average in MRO. TAT commitments based on the average are regularly missed when findings occur. Fix: percentiles and a parts strategy.
  11. Letting rush orders become the rule. Constant expediting destroys schedule stability. Fix: clear priority rules and intervention rights.
  12. Software before data. An APS is introduced before the master data is right. Fix: data quality as the first work package.
  13. Treating controlled data as an IT afterthought. ITAR or CUI orders end up in a planning system or cloud tenant that is not set up for them. Fix: clarify export control and CMMC scope before selecting or rolling out planning software [36][49].

18. iFAKT and aerospace

Note: The author works at iFAKT GmbH.

iFAKT GmbH, headquartered in Stuttgart, Germany, develops the software Polaris. According to the company website, Polaris connects ERP data with a digital twin of production in order to optimize plans. The platform includes modules for value stream and business process modeling, simulation, planning optimization (Optimizer), shop floor execution (Operator) and analytics (Analyzer) [31]. The website lists aerospace as a separate industry and describes support for suppliers and manufacturers with complex manufacturing processes [31].

As an aerospace reference, iFAKT publishes a case study with Airbus Netherlands. Since 2018, the site has built thrust frames for the propulsion modules of the Ariane 6 launch vehicle (Vulcain Aft Bay and Vinci Thrust Frame). According to the case study, the Polaris modules Optimizer, Operator and Analyzer have supported this production for seven years. The stated requirements were digital documentation, in-process quality assurance, shorter lead times, automated order scheduling and optimized resource allocation. The case study describes qualitative results such as shorter waiting times thanks to faster response to unplanned changes, shorter handover times and order status available at any time; it gives no figures [32]. The AIT manager of Airbus Netherlands is quoted as saying that the Polaris tools helped bring more structure to production [32].

On its home page, iFAKT also states improvement figures with the qualifier "up to" (for example for lead time and capacity). Because no methodology has been published for them, these figures are not used here [31].

Context: The requirements described in this guide (constraint-based scheduling, qualifications, outside operations, simulation of rate scenarios, shop floor feedback) are vendor-neutral. Polaris is one of several solutions on the market. Evaluate any system against the criteria in Section 11.3 and with a pilot using your own data. The sister article iFAKT Polaris describes the software in more detail.

19. Glossary

APQP (Advanced Product Quality Planning): Structured quality planning for new products and processes; in aerospace governed by AS9145 / EN 9145.

APS (Advanced Planning and Scheduling): Planning software that schedules against finite capacity and material availability.

As-built / as-designed: The configuration actually built versus the configuration specified by engineering.

Bottleneck (constraint): The resource that limits the throughput of the whole system.

Ladder of four planning levels from strategic to detailed scheduling.

CAMO (Continuing Airworthiness Management Organisation): EASA-approved organization that manages the continuing airworthiness of an aircraft (EASA Part-CAMO).

CMMC (Cybersecurity Maturity Model Certification): US Department of Defense program for verifying the cybersecurity of contractors that handle FCI or CUI; contract clause DFARS 252.204-7021.

CUI (Controlled Unclassified Information): Government information that requires safeguarding but is not classified; its presence in planning systems brings them into CMMC scope.

Digital thread: Continuous link of all product data across the life cycle.

Drum-buffer-rope (DBR): Theory of Constraints control principle in which the bottleneck sets the pace and limits release.

EASA Form 1: Authorized release certificate for aviation parts issued by EASA-approved production or maintenance organizations.

Effectivity: Statement of the serial number, aircraft or date from which a configuration or change applies.

Escape: A defective part that has reached the customer.

FAA Form 8130-3: FAA Authorized Release Certificate (Airworthiness Approval Tag) for domestic airworthiness approval, return to service and export; issued only by FAA-authorized persons and organizations.

FAI (First Article Inspection): Complete inspection of a first production part against all design characteristics under AS9102 / EN 9102.

Genealogy: Parent-child relationships between material, lots, parts and assemblies.

HMLV (high mix, low volume): Production of many variants in small quantities.

Key characteristic: A feature whose variation significantly affects fit, function, performance or service life; governed by AS9103 / EN 9103.

Learning curve: Relationship between cumulative quantity and effort per unit; after Wright (1936).

LLP (life-limited part): A part with an approved maximum number of cycles or hours.

MRO (maintenance, repair and overhaul): Aircraft and component maintenance services.

Nadcap: Industry-managed accreditation program for special processes, administered by the Performance Review Institute (PRI).

OTD (on-time delivery): Share of deliveries made on the committed date.

Hub of three levers that reduce MRO turnaround risk.

Part 145: In the US, the FAA repair station certificate (14 CFR Part 145); in the EU, the EASA maintenance organization approval.

Part 21 Subpart G: In the US, the FAA production certificate (14 CFR 21.131 to 21.150); in the EU, the EASA Production Organisation Approval (POA).

PMA (Parts Manufacturer Approval): FAA production approval for replacement and modification parts (14 CFR Part 21, Subpart K).

PPAP (Production Part Approval Process): Approval procedure for production parts; in aerospace part of AS9145 / EN 9145.

Rate: Production quantity per month, for example rate 75 = 75 aircraft per month.

Repair station: A maintenance organization certificated by the FAA under 14 CFR Part 145.

Special process: A process whose result cannot be fully verified on the finished part without destroying it, such as heat treating or surface treatment.

TAT (turnaround time): Time from induction of a maintenance order to return to the customer.

Tier 1 / Tier 2: Supply tiers; Tier 1 supplies the aircraft maker directly, Tier 2 supplies Tier 1.

WIP (work in process): Inventory on the shop floor.

20. FAQ: common questions about aerospace production planning

What is aerospace production planning? It is the planning of quantities, dates, capacity and material for aircraft, engine and component manufacturing, under the industry's evidence requirements. It combines high-mix, low-volume production, long lead times and outside special processes with strict traceability and configuration control. The aircraft makers' customer rates set the pace across all supply tiers.

Why is ERP scheduling not enough for aerospace? Classic MRP logic calculates with fixed lead times and without capacity limits. A feasible production schedule has to account for finite capacity, qualifications of people and machines, and slots at outside processors. APS systems or an extended detailed scheduling layer do this.

What production rate is Airbus planning for the A320 Family? According to its report on the first nine months of 2026, Airbus is aiming for 70 to 75 aircraft per month by the end of 2027, then stabilizing at rate 75 [3]. The target has slipped several times, partly because of missing engines [4].

What is Boeing's 737 production rate? In May 2026 Boeing's CEO said the 737 line was running at rate 47 [8]. Boeing's third-quarter 2026 release describes the program as progressing toward stabilized production of 47 per month [47]. The FAA had capped the rate at 38 after January 2024 and approved 42 in October 2025 [7].

Which standards does an aerospace supplier need to know? The core is AS9100D (EN 9100:2018). Depending on the work, add AS9102 (first article inspection), AS9103 (key characteristics), AS9145 (APQP/PPAP), AS9120 (distributors) and often Nadcap accreditation for special processes. Production approval holders work under FAA 14 CFR Part 21 (or EASA Part 21 Subpart G); defense suppliers also face ITAR/EAR, DFARS and CMMC requirements.

What is the difference between AS9100 and EN 9100? None in content. The IAQG standard is published as AS9100 by SAE International in the Americas, as EN 9100 in Europe and as JISQ 9100 in Asia [13][14].

Is AS9100D still valid? Yes. The IAQG is working on a revision to be published as IA9100. As of October 2026, the publication date and transition period had not been confirmed, and AS9100D certificates remain valid [15].

What does AS9100 require for traceability? It requires traceability of the raw materials, materials and processes used, as well as of tools and people [14]. Customers add specific requirements in their supplier quality requirements, and FAA production approval holders flow down their own quality system requirements [41].

Hub of the lead time levers based on Little's Law.

When is a first article inspection (AS9102) required? For new parts and for changes that can affect form, fit or function, for example to design, material, manufacturing source, process, tooling or location, and after a production break of more than two years. Depending on the scope, a full or partial FAI is required [34].

What is the learning curve in aircraft manufacturing, and why does it matter for planning? The learning curve describes how effort per unit falls as cumulative quantity rises. Wright showed a reduction of about 20 % per doubling in 1936 [25]. If you plan a launch with mature-rate times, you significantly underestimate the capacity required (worked example in Section 9).

How do I plan a rate ramp-up correctly? Assess each resource individually, especially the bottleneck, instead of average utilization. Calculate several rate scenarios, account for learning curves, inspection capacity, qualification times and approvals, and secure outside capacity by contract. The checklist in Section 10.3 helps.

What is Nadcap? Nadcap is an industry-managed accreditation program for special processes such as heat treating, chemical processing, welding and nondestructive testing, founded in 1990 and administered by the Performance Review Institute [21][54]. Many customers require Nadcap accreditation for special processes.

Can APS handle outside processes like heat treating? Yes, if they are modeled as resources with capacity and slots rather than as a flat lead time. Agree weekly slots with the processor, store them as a constraint and make the returned certificate a condition for the next operation (Section 7.2).

Does CMMC apply to aerospace suppliers? It applies to defense contractors and subcontractors whose contracts involve federal contract information (FCI) or controlled unclassified information (CUI). The DFARS clause took effect on November 10, 2025 and is being phased in over three years; it flows down to subcontracts that involve FCI or CUI [49].

How is MRO planning different from production planning? In maintenance, the scope of work is only known after inspection. Planning has to work with finding probabilities, parts availability and buffers. The central KPI is turnaround time.

How can a repair station reduce turnaround time? By inspecting early, stocking critical parts or providing them through exchange pools, reserving capacity for non-routine work and speeding up customer approvals. TAT commitments should be based on percentiles rather than averages.

Which KPIs matter most for aerospace suppliers? On-time delivery (OTD), lead time, work in process, bottleneck utilization, escapes and first pass yield. In maintenance, turnaround time and finding rate are added.

What does a digital twin bring to aerospace manufacturing? It enables scenarios for rates and investments, faster rescheduling during disruptions and, together with the digital thread, fast answers to traceability questions. Clean master data and confirmation data are the prerequisite.

Where are the biggest supply chain risks in 2026? According to Roland Berger, in skilled labor, raw materials such as titanium, castings and forgings, fasteners, and testing and surface treatment services [10]. For engines, supply shortages are limiting the aircraft makers' rates [4].

21. Conclusion

In 2026 the aerospace industry has full order books but a supply chain that can work through them only slowly. For suppliers and maintenance shops, production planning has become a competitive factor. Those who know their bottlenecks, plan learning curves and special processes realistically, build traceability into the order flow and calculate rate scenarios in advance can follow ramp-ups without sacrificing on-time delivery and quality.

The path there rarely starts with software. It starts with measurement, clean master data and simple control rules such as limited WIP and bottleneck-based release. APS, simulation and digital twins strengthen these foundations; they do not replace them. The mechanisms are well known and have been documented for decades, from Wright's learning curve to Little's Law and the Theory of Constraints. Applying them consistently is the real task.

Further reading on m365.fm

Post and podcast

Entity pages

Lead Time · Advanced Planning and Scheduling · Constraint-based Scheduling · Theory of Constraints · Enterprise Resource Planning · Digital Twin · Factory Simulation · Philip Schubert · iFAKT · Polaris · Mirko Peters

Related guides

Go deeper: related articles

Note: The author works at iFAKT GmbH.

Sources

All online sources were retrieved on November 20, 2026.

  1. BDLI (German Aerospace Industries Association): BDLI Industry Data 2026: Aerospace Industry Sets New Records for Revenue and Employment. Press release, Berlin, May 27, 2026. https://www.bdli.de/en/meldungen/bdli-branchendaten-2026-luft-und-raumfahrtindustrie-erreicht-neue-rekorde-bei-umsatz-und
  2. Nasdaq/RTTNews: Airbus Delivers 793 Aircraft In 2025 As Order Backlog Reaches Record Level. January 2026. https://www.nasdaq.com/articles/airbus-delivers-793-aircraft-2025-order-backlog-reaches-record-level
  3. Airbus: Airbus reports Nine-Month (9m) 2026 results. Press release, October 28, 2026. https://www.airbus.com/en/newsroom/press-releases/2026-10-airbus-reports-nine-month-9m-2026-results
  4. Aerospace Global News: Airbus accuses Pratt & Whitney of failing to deliver as A320 ramp up stalls. April 15, 2026. https://aerospaceglobalnews.com/news/airbus-pratt-whitney-a320-ramp-up/
  5. Terminair: Airbus delivers 74 aircraft in October, needs 249 more by year-end for its 870 target. November 5, 2026. https://terminair.com/story/113485-airbus-delivers-74-aircraft-in-october-needs-249
  6. Boeing: Boeing Reports Fourth-Quarter Results. Press release, January 27, 2026. https://boeing.mediaroom.com/2026-01-27-Boeing-Reports-Fourth-Quarter-Results
  7. Assembly Magazine: Boeing Cleared to Boost Production of 737 MAX. October 22, 2025. https://www.assemblymag.com/articles/99622-boeing-cleared-to-boost-production-of-737-max
  8. CAPA Centre for Aviation: Boeing testing production rate of 47 aircraft per month, cautious of increasing to 52: CEO. May 28, 2026. https://centreforaviation.com/news/boeing-testing-production-rate-of-47-aircraft-per-month-cautious-of-increasing-to-52-ceo-1360867
  9. ADS Group (summary of the IATA release): Supply chain challenges could cost airlines over $11bn in 2025. October 14, 2025; study "Reviving the Commercial Aircraft Supply Chain" by IATA and Oliver Wyman. https://www.adsgroup.org.uk/knowledge/industry-member-news/supply-chain-challenges-could-cost-airlines-over-11bn-in-2025/
  10. Roland Berger: Global Aerospace Supply Chain Study 2026. June 2026 (survey of 95 companies, January/February 2026). https://mailing.rolandberger.com/hubfs/07_presse/Aerospace%20Supply%20Chain%20Study%202026%20Roland%20Berger.pdf
  11. CNBC: RTX to take $3 billion charge on Pratt & Whitney engine problem. September 11, 2023. https://www.cnbc.com/2023/09/11/rtx-to-take-3-billion-charge-on-pratt-whitney-engine-problem.html
  12. Malay Mail (Reuters): Boeing suspends Russian titanium as Airbus keeps buying. March 8, 2022. https://www.malaymail.com/news/money---international/2022/03/08/boeing-suspends-russian-titanium-as-airbus-keeps-buying/2046061
  13. IAQG: Standards (overview of the 9100 family). https://ma.iaqg.org/standards
  14. TÜV Rheinland: FAQ EN/AS 9100ff. series of standards (German). https://certification.tuv.com/content-media-files/master-content/services/systems/0403-tuv-rheinland-en-as-9100ff-series-of-standards/tuv-rheinland-en-as-9100-faq-de.pdf
  15. The QMS Collective: The Current AS9100 Revision, and How to Read Dates That Keep Slipping. October 16, 2026. https://theqmscollective.com/blog/current-as9100-revision-confirmed-vs-expected-ia9100
  16. Estonian Centre for Standardisation (EVS): EVS-EN 9145:2018 Aerospace series – Requirements for Advanced Product Quality Planning and Production Part Approval Process. https://www.evs.ee/en/evs-en-9145-2018
  17. DIN Media: DIN EN 9102:2025-01, Aerospace series – Quality management systems – First article inspection requirement (EN 9102:2024). https://www.dinmedia.de/en/standard/din-en-9102/377807227
  18. Net-Inspect: AS9102 First Article Inspection Report Rev B vs Rev C. https://www.net-inspect.com/blog/as9102-rev-b-vs-rev-c/
  19. IAQG: 9103 Variation Management of Key Characteristics. https://iaqg.org/standard/9103-variation-management-of-key-characteristics/ ; EVS-EN 9103:2023: https://www.evs.ee/en/evs-en-9103-2023
  20. EVS: EVS-EN 9110:2018 Quality Management Systems – Requirements for Aviation Maintenance Organizations. https://www.evs.ee/en/evs-en-9110-2018
  21. Wikipedia: Nadcap. https://en.wikipedia.org/wiki/Nadcap
  22. EASA: Easy Access Rules for Initial Airworthiness and Environmental Protection (Part 21), 21.A.131 Scope (Subpart G). https://www.easa.europa.eu/en/document-library/easy-access-rules/online-publications/easy-access-rules-initial-airworthiness-and?page=13
  23. EASA: Easy Access Rules for Continuing Airworthiness (Regulation (EU) No 1321/2014 with Part-M, Part-145, Part-CAMO; amending Regulation (EU) 2019/1383). https://www.easa.europa.eu/en/document-library/easy-access-rules/online-publications/easy-access-rules-continuing-airworthiness?page=66
  24. Wright, T. P.: Factors Affecting the Cost of Airplanes. Journal of the Aeronautical Sciences, vol. 3, no. 4 (1936), pp. 122–128. Reference: https://en.wikipedia.org/wiki/Theodore_Paul_Wright
  25. Wikipedia: Experience curve effect. https://en.wikipedia.org/wiki/Experience_curve_effect
  26. U.S. Government Accountability Office (GAO): Cost Estimating and Assessment Guide, Cumulative Average Formulation. https://gaoinnovations.gov/cost-guide/cumulative-average-formulation.html
  27. Little, John D. C.: A Proof for the Queuing Formula L = λW. Operations Research, vol. 9, no. 3 (1961), pp. 383–387.
  28. Goldratt, Eliyahu M.; Cox, Jeff: The Goal. A Process of Ongoing Improvement. North River Press, 1984.
  29. Oliver Wyman: Why engine availability is a growing challenge for aviation. September 24, 2026. https://www.oliverwyman.com/our-expertise/insights/2026/sep/aviation-engine-availaibility-bottlenecks.html
  30. Oliver Wyman / ARSA: Global Fleet & MRO Market Forecast 2026–2036, Executive Summary. 2026. https://arsa.org/wp-content/uploads/2026/03/ARSA-OW-2026FleetMROMarketReport-ExecSum-2026.pdf
  31. iFAKT GmbH: website (home page, solutions, contact, imprint). https://www.ifakt.de/
  32. iFAKT GmbH: Customer Reference Airbus Netherlands. https://www.ifakt.de/references/Airbus_Netherlands_Reference.pdf
  33. 4flow: Advanced planning in multi-level production networks in aviation and aerospace. https://4flow.com/blog/advanced-planning-in-multi-level-production-networks-in-aviation-and-aerospace
  34. InspectionXpert: When to Conduct a First Article Inspection. https://www.inspectionxpert.com/blog/when-to-conduct-a-first-article-inspection
  35. IAQG: 9145 Guidance Presentation (APQP phases, PPAP elements). https://ma.iaqg.org/wp-content/uploads/2019/10/9145-Guidance-Presentation.pdf
  36. Electronic Code of Federal Regulations: International Traffic in Arms Regulations, 22 CFR Parts 120–130 (https://www.ecfr.gov/current/title-22/chapter-I/subchapter-M); Export Administration Regulations, 15 CFR Parts 730–774 (https://www.ecfr.gov/current/title-15/subtitle-B/chapter-VII/subchapter-C).
  37. Produktion (German trade journal): Nachweispflicht als Nadelöhr: Warum die Rückverfolgbarkeit über Millionenaufträge in der Verteidigungsindustrie entscheidet ("Evidence requirements as a bottleneck: why traceability decides multi-million defense contracts"). October 27, 2026. https://www.produktion.de/ruestung-aerospace/nachweispflicht-als-nadeloehr-warum-die-rueckverfolgbarkeit-ueber-millionenauftraege-in-der-verteidigungsindustrie-entscheidet/2758489
  38. Kingman, J. F. C.: The single server queue in heavy traffic. Mathematical Proceedings of the Cambridge Philosophical Society, vol. 57, no. 4 (1961), pp. 902–904.
  39. Defence Agenda: Airbus Keeps Production Ramp-Up Targets Unchanged. August 1, 2026. https://defenceagenda.com/airbus-production-ramp-up-targets-h1-2026
  40. Martin, James R.: Learning Curve Summary (cumulative average model after Wright, incremental unit model after Crawford). Management And Accounting Web. https://maaw.info/LearningCurveSummary.htm
  41. 14 CFR 21.137 Quality system (production certificates), 14 CFR 21.307 Quality system (PMA), and table of subparts of 14 CFR Part 21. Legal Information Institute, Cornell Law School. https://www.law.cornell.edu/cfr/text/14/21.137 ; https://www.law.cornell.edu/cfr/text/14/21.307 ; https://www.law.cornell.edu/cfr/text/14/part-21 (official text: https://www.ecfr.gov/current/title-14/chapter-I/subchapter-C/part-21/subpart-G)
  42. Electronic Code of Federal Regulations: 14 CFR Part 145 Repair Stations (145.1, 145.59, 145.109, 145.163, 145.201, 145.219). https://www.ecfr.gov/current/title-14/chapter-I/subchapter-H/part-145
  43. FAA: Order 8130.21H, Procedures for Completion and Use of the Authorized Release Certificate, FAA Form 8130-3, Airworthiness Approval Tag. Effective February 1, 2014. https://www.faa.gov/documentLibrary/media/Order/FAA_Order_8130.21H.pdf
  44. SAE International: AS9100D Quality Management Systems – Requirements for Aviation, Space, and Defense Organizations (revised September 20, 2016). https://saemobilus.sae.org/standards/as9100d-quality-management-systems-requirements-aviation-space-defense-organizations
  45. SAE International: AS9145 Aerospace Series – Requirements for Advanced Product Quality Planning and Production Part Approval Process (issued November 8, 2016). https://saemobilus.sae.org/standards/as9145-aerospace-series-requirements-advanced-product-quality-planning-production-part-approval-process
  46. ANSI Webstore: SAE AS9102C-2023, Aerospace Series – First Article Inspection Requirements. https://webstore.ansi.org/standards/sae/sae9102c2023
  47. Boeing: Boeing Reports Third-Quarter Results. Press release, Arlington, Va., October 27, 2026. https://boeing.mediaroom.com/2026-10-27-Boeing-Reports-Third-Quarter-Results
  48. Aerospace Industries Association (AIA): 2026 AIA Facts & Figures: U.S. Aerospace & Defense Industry Leads the World with $1 Trillion in Sales. June 25, 2026 (with S&P Global Market Intelligence, 2025 data). https://www.aia-aerospace.org/?p=27492 ; overview: https://aia-aerospace.org/industry-impact
  49. Federal Register, vol. 90, no. 173 (September 10, 2025): Defense Federal Acquisition Regulation Supplement: Assessing Contractor Implementation of Cybersecurity Requirements (DFARS Case 2019-D041), effective November 10, 2025. https://www.govinfo.gov/content/pkg/FR-2025-09-10/html/2025-17359.htm
  50. U.S. Department of Defense, Office of Small Business Programs: Cybersecurity Maturity Model Certification (CMMC) 2.0. https://business.defense.gov/Programs/Cyber-Security-Resources/CMMC-20
  51. 48 CFR 252.225-7009 Restriction on Acquisition of Certain Articles Containing Specialty Metals. Legal Information Institute, Cornell Law School. https://www.law.cornell.edu/cfr/text/48/252.225-7009
  52. FAA: Advisory Circular AC 21-29D, Detecting and Reporting Suspected Unapproved Parts. July 12, 2016. https://www.faa.gov/documentLibrary/media/Advisory_Circular/AC_21-29D.pdf
  53. 14 CFR 91.417 Maintenance records. Legal Information Institute, Cornell Law School. https://www.law.cornell.edu/cfr/text/14/91.417
  54. Boeing Suppliers: Nadcap Accreditation FAQ (Nadcap as an "industry-managed approach to conformity assessment of 'special processes'", administered by PRI). https://www.boeingsuppliers.com/nadcap/nadcap_faq.htm
  55. Aerospace Manufacturing (aero-mag.com): Lack of capacity planning adding to ramp-up challenge, report reveals (Vendigital rate readiness assessment, 100+ suppliers). Undated. https://www.aero-mag.com/lack-of-capacity-planning-adding-to-ramp-up-challenge-report-reveals