Digital Twin in Manufacturing: The Complete Guide to Factory Simulation, Material Flow and Virtual Commissioning

Guide · Step 7 of 10 · 58 min read · Updated · View the whole path · Deutsche Fassung

Header graphic: three key points of a production digital twin.

Last updated: November 20, 2026 · Technically reviewed against the standards, primary sources and publications listed under Sources

Short answer: A digital twin in manufacturing is an executable digital representation of a factory's products, processes and resources that is updated with data from real operations, ideally automatically. You use it to simulate operations, assess bottlenecks and scenarios in advance, commission control software virtually and make decisions before you change anything on the real shop floor.

The term "digital twin" is used so loosely that it has almost stopped meaning anything. A 3D model of a building is called a digital twin. So is a dashboard of machine data, and sometimes a capacity spreadsheet with red, yellow and green cells. For plant and operations leaders that is a real problem: if you do not know exactly what you want to build, you buy the wrong thing, collect data without a question to answer and end up a year later with an expensive visualization project that does not improve a single decision.

This guide clears up the terminology and walks you through every layer: from the origin of the concept with Michael Grieves and NASA, through the standards (ISO 23247, ISA-95, the Asset Administration Shell, and the German VDI guidelines on simulation and virtual commissioning that much of the industry still works from), to the practical question of how to derive a useful production twin from the data that already sits in your ERP system. The focus is on what manufacturing teams actually decide: factory and layout planning, capacity and bottlenecks, product mix, schedule quality, virtual commissioning and the sizing of automated guided vehicle (AGV) fleets. For a compact definition, see the entity page Digital Twin.

Key takeaways

Reading paths for busy readers

You are a ...Read first
Manufacturing engineer or factory plannerSections 2, 6, 7 and 10 (definitions, simulation, use cases, roadmap)
Plant manager, VP of operations, executiveShort answer, sections 4, 12 and 13 (maturity, cost and benefit, common mistakes)
Controls or automation engineerSection 7.5 (virtual commissioning) and 14 (standards)
Intralogistics, AGV/AMR project leadSection 7.6 (AGV and AMR fleet planning)
M365/Azure admin, IT/OT architectSections 5, 8 and 16 (architecture, Microsoft services, security)

Table of contents

  1. What is a digital twin in manufacturing?
  2. Digital model vs. digital shadow vs. digital twin
  3. Types of digital twins in manufacturing
  4. Maturity levels: from representation to self-optimizing system
  5. Architecture and data foundation: ERP, MES, PLM, IoT
  6. Simulation at the core: factory, material flow and value stream simulation
  7. Use cases and the data each one needs
  8. Digital twins with Microsoft Azure and Fabric
  9. Artificial intelligence and the digital twin
  10. Roadmap: implementation in six phases
  11. Data quality: the underrated prerequisite
  12. Cost and benefit, assessed honestly
  13. Common mistakes and how to avoid them
  14. Standards and guidelines at a glance
  15. Software categories: a neutral comparison
  16. Security, data ownership and regulation
  17. Building a twin from ERP and value stream data with iFAKT Polaris
  18. Glossary
  19. FAQ: digital twins in manufacturing
  20. Conclusion

1. What is a digital twin in manufacturing?

A working definition

In manufacturing practice, a working definition with three conditions has proven useful:

  1. It represents a real counterpart. The twin stands for a specific object (a machine, a line, a plant) or a specific process, not a generic class.
  2. It is executable. It holds not only structure and geometry but also behavior. It can advance states, play through operations and answer "what happens if ...?" questions.
  3. It is connected to reality by data. It is updated from operating data, ideally automatically, and its results flow back into decisions or controls.

Without point 2, you have a database or a 3D model. Without point 3, you have a simulation model. Both are useful, but neither is a twin in the narrow sense.

US institutions define the term along the same lines. The Digital Twin Consortium's definition from December 3, 2020 calls a digital twin "a virtual representation of real-world entities and processes, synchronized at a specified frequency and fidelity" [51]. The 2024 consensus report of the National Academies of Sciences, Engineering, and Medicine, sponsored by the US Department of Defense, the Department of Energy, the National Institutes of Health and the National Science Foundation, describes a digital twin as a set of virtual information constructs that mimics the structure, context and behavior of a system, "is dynamically updated with data from its physical twin, has a predictive capability, and informs decisions that realize value," and adds: "The bidirectional interaction between the virtual and the physical is central to the digital twin" [50]. NIST describes digital twins as electronic representations of real-world entities that let people observe those entities and their state changes, and examines the security and trust issues they raise [49]. All three definitions contain the same elements as the working definition above: a real counterpart, behavior and a data connection.

Digital twin, smart factory, digital factory: terms sorted out

In English, you will see "digital twin in manufacturing", "manufacturing digital twin", "factory digital twin" and "production digital twin" used for the same concept. The smart factory (or smart manufacturing) is something else: a connected, largely self-organizing plant as the target picture of Industry 4.0. The digital twin is one of its tools, not a synonym. The digital factory is an older, planning-oriented umbrella term from the German guideline VDI 4499 for digital models, methods and tools (see below); in North America the closest everyday terms are "digital manufacturing" and "virtual manufacturing". Terms such as production simulation, factory simulation and material flow simulation describe methods a digital twin can use. Digital thread describes the connected flow of information across the lifecycle; ISO 23247-5 now addresses it explicitly [7].

Origins: from Grieves and NASA to Industry 4.0

The concept comes from product lifecycle management (PLM). Michael Grieves presented a model in 2002 that linked a real space, a virtual space and the flow of data and information between them. He dates the first presentation to a management forum of the Society of Manufacturing Engineers (SME) in October 2002 and a presentation at the University of Michigan in December 2002 [2]. The model was first called the "Mirrored Spaces Model" (2005), then the "Information Mirroring Model" (2006) and later "Digital Twin"; according to Grieves, the concept itself stayed the same [2]. Grieves credits the name "digital twin" to John Vickers of NASA [1][2]. Other authors point out that the origin story cannot be documented without gaps and that there were earlier precursors, such as research on virtual manufacturing in the 1990s [4].

The term gained wide attention through aerospace. NASA described the digital twin in its technology roadmap "Modeling, Simulation, Information Technology & Processing" (Shafto et al., draft 2010) [4]. In 2012, Glaessgen and Stargel formulated the often-quoted definition for NASA and the US Air Force of a digital twin as an "integrated multiphysics, multiscale, probabilistic simulation of an as-built vehicle or system" that combines ultra-high-fidelity simulation with health monitoring, maintenance history and fleet data to mirror the life of its flying twin [3].

In German manufacturing, the term became tied to Industrie 4.0 from the mid-2010s. There it met an older, independent tradition: the Digital Factory (VDI 4499) and discrete event simulation of material flow (VDI 3633). In the US, factory simulation grew from operations research and industrial engineering, with textbooks such as Law's [41] and commercial discrete event tools. On both sides of the Atlantic, many tools marketed today as digital twins are methodologically descendants of this factory simulation. For more context, see the entity page Industry 4.0.

Formal definitions in standards

Formal standards have existed since 2021. ISO 23247 ("Automation systems and integration: Digital twin framework for manufacturing") defines a framework for digital twins in manufacturing. Parts 1 to 4 (overview, reference architecture, digital representation of manufacturing elements, information exchange) were published in October 2021 (Part 1 on October 21, 2021) [6]. Part 5 ("Digital thread for digital twin") and Part 6 ("Digital twin composition", published July 14, 2026) followed in 2026 [7][8]. ISO/IEC 30173:2023 sets cross-industry terms and concepts, including lifecycle processes, types of digital twins, a functional view and stakeholders [9].

For US manufacturers, NIST offers a practical entry point into ISO 23247. Its report Use Case Scenarios for Digital Twin Implementation Based on ISO 23247 (NIST AMS 400-2, Guodong Shao, May 2021) was written explicitly to reduce the confusion about digital twins among small and mid-sized manufacturers and walks through three use cases built on the framework [47]. NIST's ongoing project "Digital Twins for Advanced Manufacturing" contributes to ISO 23247, works on a reference implementation of Part 5 (digital thread) and proposes a verification, validation and uncertainty quantification (VVUQ) framework as a future Part 7; it names the "lack of standards" as a main barrier to adoption [48].

For factory planning, the German definition of the Digital Factory in VDI 4499 Part 1 remains influential. The 2008 edition reads (our translation): "The Digital Factory is the generic term for a comprehensive network of digital models, methods and tools, including simulation and three-dimensional visualization, that are integrated by continuous data management. Its aim is the holistic planning, evaluation and ongoing improvement of all essential structures, processes and resources of the real factory in conjunction with the product." [17] A new edition of VDI 4499 Part 1 appeared in April 2026, covering the term, objectives, processes, data management and system architecture of the Digital Factory [16]. If you quote it, check whether the wording of the new edition differs.

Note the phrase "structures, processes and resources ... in conjunction with the product". It already contains the product-process-resource thinking that a production twin is built on (see section 5, "The product-process-resource model at the core").

Comparison of digital shadow and digital twin data flow.

2. Digital model vs. digital shadow vs. digital twin

The most-cited distinction for manufacturing comes from Kritzinger, Karner, Traar, Henjes and Sihn (Fraunhofer Austria) in 2018 [5]. They distinguish three levels of integration based on how data flows between the physical and the digital object.

AttributeDigital modelDigital shadowDigital twin
Data flow physical → digitalmanualautomaticautomatic
Data flow digital → physicalmanualmanualautomatic
Typical examplesimulation model of a planned line, CAD layoutsimulation model updated daily with orders and confirmations from ERP/MESmodel that automatically sends production sequences or parameters back to the control system
State of the physical objectdoes not have to existexists, is observedexists, is observed and influenced
Typical usefactory planning, greenfield, capital investment decisionmonitoring, as-is analysis, forecasting, schedule validationclosed-loop control, detailed scheduling, autonomous optimization
Demands on IT and governancelowmedium (interfaces, data quality)high (real time, security, approval processes)

In their literature review, Kritzinger et al. found that publications on the highest level, the true twin, were rare, while models and shadows were described far more often [5]. That matches practice: in factory and production planning, an automatic feedback loop into the controls is often not even wanted. A planner wants to compare scenarios and then decide deliberately. A model that changes your production sequence without approval would be unacceptable in many plants, both organizationally and in terms of liability.

The consequence for your project: do not ask "Do we have a real twin?" Ask "What level of integration does the decision we want to improve require?" For a capital decision on a new assembly building, a well-validated model is enough. For a daily check of whether this week's schedule is realistic, you need a shadow with automatic data feeds. Only for closed-loop control, such as automatic sequencing at a bottleneck station, does the effort of a full twin pay off.

A second look at the "shadow": In German production engineering, "digital shadow" is sometimes used more narrowly, as a sufficiently accurate, task-specific image of production data without simulation capability. Some vendors also describe the shadow as a "static copy of historical data". These readings differ from Kritzinger et al. US sources rarely use the term "digital shadow" at all and often call every level a twin. If you use any of these terms in a request for proposal (RFP) or a requirements document, define them explicitly.

3. Types of digital twins in manufacturing

Digital twins can be classified by the object they represent and by lifecycle phase. The classification below is common in the literature and in practice but not standardized; ISO/IEC 30173 describes types of digital twins at a more general level [9]. US explainers often use a four-level scheme of component (or part) twins, asset twins, system (or unit) twins and process twins, popularized by IBM [52]. The table below is more specific to manufacturing.

TypeRepresentsTypical questionsMain data sources
Product twina product over its lifecycle (geometry, variants, properties, condition in the field)Does the design meet the requirements? How does the product behave in use?CAD, PLM, analysis (FEA, CFD), field data
Process twina manufacturing process (milling, welding, injection molding, assembly)Which parameters deliver stable quality? Where do scrap and rework arise?machine controls, sensors, quality data, process models
Machine or asset twina machine or piece of equipment with kinematics, control logic and conditionDoes the PLC logic work? When is maintenance due?mechanical CAD, electrical CAD, PLC program, condition data
Production or factory twinthe interaction of orders, processes, resources, material flow and logisticsIs there enough capacity? Where is the bottleneck? Which layout, which buffer, how many AGVs?ERP, MES, value stream data, layout, shift patterns
Performance or operations twinongoing performance metrics of a systemHow are OEE, lead time, on-time delivery and energy use trending?MES, production data collection, energy meters, IoT
Supply chain twinsuppliers, sites, transportation, inventoryWhat happens if a supplier fails? Where should we hold safety stock?ERP, SCM, logistics data

The types are not sharply separated; they nest. A factory twin can embed a more detailed asset twin for a single bottleneck machine. Composition of several twins is exactly what the new Part 6 of ISO 23247 covers [8].

Lifecycle phases: Many authors also distinguish the twin "as designed" (planning state), "as built" (actually built) and "as operated" or "as maintained" (in operation). This matters for factory planning: a planning model describes a plant that does not exist yet, so it must not be confused with operating data that cannot exist yet.

Levels of detail: In discrete event simulation, you also distinguish levels of aggregation, from the network and plant level through area, line and cell down to the single machine. VDI 3633 covers machine-level simulation with 3D motion and process simulation in a separate part [13]. The skill is to choose the level as coarse as possible and as fine as necessary.

4. Maturity levels: from representation to self-optimizing system

Maturity models help you assess your starting point and set realistic goals. In German-speaking countries, the acatech Industrie 4.0 Maturity Index is widely used (acatech is the German National Academy of Science and Engineering). It describes six development stages and assesses resources, information systems, culture and organizational structure; the updated edition appeared in 2020 [20]. The stages are computerization, connectivity, visibility, transparency, predictive capacity and adaptability.

For the digital twin, this translates into a practical scale:

LevelGuiding questionWhat the twin deliversPrerequisite
1 RepresentWhat do we have?structured model of products, processes, resources (master data, layout)maintained master data, consistent naming
2 ObserveWhat is happening?current state from confirmations, machine data, inventory (visibility)interfaces to ERP/MES, timestamps
3 UnderstandWhy is it happening?root-cause analysis, bottleneck identification, variance analysis (transparency)historized data, metric definitions
4 PredictWhat will happen?simulation and forecasting of lead time, utilization, due datesvalidated simulation model, planning data
5 RecommendWhat should we do?scenario comparison, optimization, recommended actionsobjective function, optimization methods
6 ActWhat happens automatically?closed loop into control (adaptability)approval concept, IT security, clear accountability

In consulting and vendor material, you will often see a shorter three-way split into descriptive, predictive and prescriptive twins. It corresponds roughly to levels 2 to 3, 4 and 5 to 6 in the table.

Important: The levels are not a mandatory sequence. A factory planning twin can be very valuable at level 4 without ever reaching level 2, because the planned plant does not exist yet. Conversely, a monitoring dashboard at level 2 is not a stepping stone to simulation if its data model contains no process logic. Plan the levels along your question, not along a model.

5. Architecture and data foundation: ERP, MES, PLM, IoT

The ISO 23247 reference model

ISO 23247-2 organizes a manufacturing digital twin into domains [6][43]:

Three steps that define a manufacturing digital twin.

This model is vendor-neutral and works well as the outline of a requirements document or RFP. NIST used exactly this structure for its three ISO 23247 use-case scenarios [47]. Above all, it makes one point clear: the twin is not the visualization. It is the layer in between that represents, synchronizes and computes.

Systems by ISA-95 level: who supplies which data?

The ISA-95 standard (ANSI/ISA-95, internationally IEC 62264) organizes a plant's systems into levels based on the Purdue model [58][19][42]: level 0 is the physical process, level 1 sensing and actuation, level 2 process control (PLC, SCADA, HMI), level 3 manufacturing operations management (MES) and level 4 business planning and logistics (ERP). ISA notes that the standard primarily deals with the interface between levels 3 and 4 [58]. For the digital twin, this gives you a clear data map:

System (level)Supplies to the twinTypical granularityTypical weaknesses
ERP (4)material master, bills of materials, routings, work centers, capacities, shift calendars, sales and production orders, confirmationsorder, operation, day/shiftstandard times outdated, setup times flat, work center groups too coarse
MES (3)actual times, downtime reasons, quantities, scrap, labor assignment, sequencesoperation, minuteinconsistent downtime reason codes, gaps in manual entries
PLM/CADproduct structure (EBOM), geometry, variants, revision levelspart, versionEBOM and manufacturing BOM (MBOM) out of sync
Layout/factory CADfloor space, aisles, positions, conveyorsfoot/meterlayouts outdated, brownfield often undocumented
PLC/SCADA (2)states, cycle times, signalsmillisecond to secondlittle meaning without context (which order?)
IoT/sensors (1)energy, temperature, vibration, position (e.g., AGVs)secondhigh data volume, missing asset mapping
Warehouse/intralogistics (WMS, AGV fleet manager)inventory, transport orders, travel timesorder, secondtravel times often not historized

For a production and factory twin, most of the structure you need sits at levels 3 and 4. Machine data from levels 1 and 2 improves distributions and downtime models but is rarely the starting point. If you do connect machines, two open standards matter most: OPC UA (IEC 62541) and, common in US machine shops, MTConnect, an open standard for manufacturing data interoperability that is also published as an ANSI standard (ANSI/MTC1.4-2018) [57]. NIST lists an MTConnect interface for digital twins among its project work [48]. The post From ERP to the shop floor: the digital twin shows what that bridge from ERP to the shop floor looks like in practice. For ERP basics, see the entity page Enterprise Resource Planning.

The product-process-resource model at the core

In digital factory practice, the product-process-resource (PPR) model has become the structuring principle. It links three views:

The value lies in the edges between the nodes: which operation consumes which assembly, on which resource, with what time, under which constraint? Model this network as a graph, and you can automatically derive network diagrams, critical paths, bottleneck resources and simulation models from it. Such a graph is also the semantic foundation on which planning algorithms and AI services can work.

The advantage over a pure 3D or IoT twin is practical: the PPR model answers the questions that production and factory planners ask every day (capacity, lead time, bottleneck, labor requirements), and much of it can be built from data that already exists.

Building the twin from ERP and value stream data

The usual digital twin story starts with sensors. For production questions, that is often the wrong place to start. Your ERP system already contains the blueprint of your plant in structured form:

ERP objectRole in the twin
Material master and bill of materials (manufacturing BOM, MBOM)product structure, requirements explosion, assembly sequence
Routing with operationsprocess logic, sequence, standard times for setup and run
Work center or work center groupresources, available capacity, cost center
Factory calendar and shift patternsavailable time, breaks, extra shifts
Sales orders and forecastsload, product mix, due dates
Production orders and confirmationsactual times, actual quantities, scrap, progress
Inventory and MRP parametersbuffers, safety stock, lot-sizing rules

Value stream mapping provides the second, complementary view: it makes material and information flows, inventory between processes and the control logic (push, pull, supermarket, FIFO) visible, which ERP tables contain only indirectly. Mike Rother and John Shook popularized the method in 1998 with Learning to See, published by the Lean Enterprise Institute [40]. Combine value stream logic with ERP master data and confirmations, and you get a model that captures both the structure and the dynamics of a production system. The episode Value Stream Mapping as a Live Data Model shows how a value stream map becomes a living data model; the method itself is explained on the entity page Value Stream Mapping, and in depth in our guide to value stream mapping.

This discussion is not new in the literature. As early as 2014, Türck, Weimer, Schubert and Drees described in the German journal Zeitschrift für wirtschaftlichen Fabrikbetrieb (ZWF) the step from static value stream mapping and its metrics to dynamic simulation of value streams, and asked which optimization options open up once time is added as a dimension [31]. In 2023, Böhm, Drees, Sai, Erlach, Stambera and Teriete presented in ZWF a universal data interface for digital value stream services that uses event-based production data as a common basis for metric calculation and visualization; it was tested in the German research project ECOWERT [32].

Semantics and interoperability: Asset Administration Shell, OPC UA, DTDL

A twin that lives only in a proprietary database is hard to extend. Three standards shape interoperability:

None of these standards alone is enough for production planning twins, because they mainly describe assets, not process logic and order dynamics. In practice, you therefore combine a planning model (PPR, simulation) with standardized asset descriptions for connectivity.

6. Simulation at the core: factory, material flow and value stream simulation

What simulation does and why static calculations fall short

VDI 3633 Part 1 (December 2014 edition), the German reference guideline, describes the fundamentals of simulating logistics, material flow and production systems and addresses planners, suppliers and operators [13]. It defines simulation as reproducing a system with its dynamic processes in a model you can experiment with, in order to gain insights that can be transferred to reality [13][30]. Law's textbook, widely used in US industrial engineering programs, covers the same ground from the statistical side [41].

The decisive point is dynamics. A spreadsheet capacity calculation works with averages: demand times processing time, divided by available time, gives utilization. If every value is below 100 percent, the plan seems to work. In reality, arrivals, processing times, setup times and breakdowns vary. Queueing theory shows that with variable times, waiting times grow disproportionately as utilization rises, and large queues build up in front of a station that runs close to its capacity limit. Interactions between stations (blocking, starving, shared resources such as operators or cranes) cannot be captured by a static calculation at all.

Worked example: For a single station, Kingman's approximation gives a sense of scale [46]. The average waiting time in front of the station is approximately W ≈ (cₐ² + cₛ²) / 2 · u / (1 − u) · t, where u is utilization, t is the mean processing time and cₐ and cₛ are the coefficients of variation of interarrival and processing times. Assume a processing time of 10 minutes and moderate variability (both coefficients of variation equal to 1):

Product-process-resource model as the core of a production twin.
Utilization uFactor u / (1 − u)Average wait in front of the station
70%2.3approx. 23 minutes
80%4approx. 40 minutes
90%9approx. 90 minutes
95%19approx. 190 minutes

The capacity spreadsheet says "fits" in all four cases. In fact, the waiting time almost quintuples between 80 and 95 percent utilization. In a line with several stations, setups and breakdowns, the effect becomes even stronger and hard to handle analytically. This is where simulation comes in.

Little's Law remains a useful sanity check: in steady state, the average inventory in a system equals the average throughput rate times the average lead time (L = λ · W) [37]. Little's Law tells you which lead time matches a given inventory, but not which inventory will result from a given level of variability. For that, you need simulation.

Types of simulation compared

AttributeDiscrete event simulation (DES)Continuous simulation / system dynamicsAgent-based simulation (ABS)Physics and 3D motion simulation
Time advancejumps from event to event (arrival, end of processing, breakdown)continuous in small time steps, differential equationsevent- or time-step-driven, depending on the toolfine time steps, kinematics and dynamics
Model elementssources, sinks, stations, buffers, conveyors, resources, ordersstocks, flows, feedback loopsautonomous agents with rules and states (vehicles, people, orders)rigid bodies, joints, sensors, control signals
Typical questionsthroughput, lead time, utilization, bottleneck, buffer sizes, labor requirementsstrategic capacity and market development, bullwhip effectAGV traffic, pedestrian flows, decentralized control, negotiation logicreachability, collision, cycle time of a robot cell, control testing
Level of detailline to plantplant to network, highly aggregatedlocal to networkcell, machine
Strengthsestablished, easy to validate, randomness built infast, good for feedback and long horizonsemergent behavior, individual rulesrealistic geometry and physics
Limitsgeometry usually simplifiedno individual ordersparameterization and validation demandingcompute-intensive, small slice of the system
ReferenceVDI 3633 [13], Law [41]Forrester, Industrial Dynamics (MIT) [38]no dedicated VDI guideline known unverifiedVDI 3633 Part 8 (machine-level simulation) [13], VDI/VDE 3693 [14]

In production and factory simulation, discrete event simulation dominates. Many modern tools combine paradigms, such as discrete event production with agent-based vehicles or a continuous energy model. Law's textbook describes the methodological fundamentals of discrete event simulation in detail, from random numbers and input distributions to statistical analysis [41].

Material flow simulation and factory simulation

The terms are often used interchangeably but have different emphases:

For more on factory simulation, see the entity page Factory Simulation.

Value stream simulation: dynamic value stream mapping

Classic value stream mapping is a snapshot based on averages. It shows inventory, lead times and flow on a given day, but not how the value stream behaves when the product mix changes, breakdowns occur or lot sizes change. Value stream simulation closes this gap by treating the value stream map as an executable model. The 2014 ZWF publication mentioned above describes exactly this step from static metrics to a dynamic view over time [31].

The practical advantage: the value stream map is familiar and accepted in the company. If you derive a simulation model from it, operations teams do not have to learn a new modeling world. The limits are very complex material flows with conveyors and warehouse logic, which call for classic material flow simulation.

How a simulation study runs

VDI 3633 describes the preparation, execution and evaluation of simulation studies [13]. The following sequence has proven itself:

  1. Objective: Which decision are you preparing? Which metrics decide it (throughput, lead time, on-time delivery, cost)?
  2. System boundary: What belongs in the model and what does not? What level of detail is needed?
  3. Data collection and preparation: master data, times, distributions, breakdowns, shift patterns (see section 11).
  4. Model building: conceptual model first, then the executable model.
  5. Verification and validation: Is the model built right (verification)? Does it represent reality accurately enough (validation)? Compare with actual data and sanity-check with subject-matter experts.
  6. Experiment design: scenarios, warm-up period, run length, number of replications.
  7. Execution and analysis: metrics with confidence intervals instead of single values, sensitivity analyses.
  8. Documentation and handover: assumptions, limits, recommendations.

Two points are neglected especially often in practice: the warm-up period (a model that starts empty produces distorted metrics for the first simulated days) and replications (a stochastic model gives different results on every run; only several runs support a reliable statement) [41]. The same verification and validation logic is what NIST wants to formalize for manufacturing twins with its proposed VVUQ framework [48].

7. Use cases and the data each one needs

The table below sorts the most important manufacturing use cases by integration level and data requirements. Treat it as a planning aid: for your case, check the "Minimum data" column first.

Use caseTypical decisionIntegration levelMinimum dataValue-adding extra data
Factory and layout planningbuilding structure, arrangement, floor space, aislesmodelproduct program, routings, times, space requirements, layout variantstransport matrices, building constraints, 3D scan
Capacity and capital investment planningadditional machine, shift or outsourcingmodel or shadowforecasts, routings, work centers, shift patterns, availabilitybreakdown distributions, setup matrices
Bottleneck analysisWhere to invest, where to relieve?shadowtime-stamped confirmations, actual times, inventorymachine states, downtime reasons
Product mix and scenario analysisnew product, variant mix, lot sizesmodel or shadowbills of materials, routings, mix scenariossetup families, sequencing rules
Schedule validation and APSIs this week's schedule feasible? Which sequence?shadow to twinorders, due dates, routings, capacities, current progressmaterial availability, people with skills
Virtual commissioningtest control software before physical commissioningmodel (equipment model with real or emulated controller)mechanical and electrical design, PLC program, I/O lists, behavior modelssafety functions, operating concepts
AGV and AMR fleet planningnumber of vehicles, routes, charging strategymodel, later shadowtransport orders (source, destination, quantity, time), layout, vehicle datatraffic rules, charging infrastructure, mixed traffic
Energy and CO2 assessmentpeak loads, shift moves, shutdown strategiesshadowpower draw per state, state data, shift patternsenergy prices, metered data per machine
Maintenancemaintenance timing, spare parts stockingshadow to twinfailure history, run hours, condition datasensors, damage models

7.1 Factory and layout planning

Factory planning is the classic field of the digital factory. In a greenfield project, the plant does not exist yet, so there is no operating data. The digital twin here is a planning model built from the product program, routings and layout variants. Its job is to compare variants under uncertainty: Which layout stays productive if the mix shifts or volume grows by a third?

Brownfield projects are different: there is data, but often no current layout. Laser scans and 3D point clouds help capture the as-built state of the building. Process logic still decides the outcome, though. A photorealistic model of the building without routings will not answer a single capacity question. Some English-language explainers call this the "visualization trap".

Proven metrics for comparing variants are throughput, lead time, work in process (WIP), transport effort (ton-miles or trips per hour), floor space and labor requirements.

Core systems that supply data to a production twin.

7.2 Capacity and bottleneck analysis

Goldratt's Theory of Constraints assumes that a system's performance is limited by one constraint, and that any improvement away from the constraint does not raise throughput [39]. The practical problem: the bottleneck is not always where the spreadsheet shows the highest utilization. It moves with the product mix, with setups and with breakdowns. A simulation model shows where orders actually pile up and which station blocks or starves others. For more on the method, see the entity page Theory of Constraints.

McKinsey describes a concrete example: in one production line, an optimized sequence at the bottleneck station reduced total processing time by about four percent [26]. Numbers like that sound small, but at a real bottleneck they translate directly into throughput.

7.3 Product mix and scenario analysis

New products, more variants, smaller lot sizes: each of these changes shifts load between resources. A twin built on a PPR model can read in new bills of materials and routings and show which resources become critical before the first part is made. McKinsey describes a metal fabrication plant whose twin, with a reinforcement-learning agent, evaluated thousands of possible product combinations across four parallel production lines [26]. Typical scenarios include:

7.4 Production scheduling and advanced planning and scheduling (APS)

APS systems create capacity-constrained schedules and sequences. A simulation twin complements them in two ways: it can play a schedule through in advance and show whether it holds under realistic variability, and it can serve as the evaluation function for optimization methods that generate many schedule variants. McKinsey reports an assembly plant where a redesigned production schedule reduced overtime and led to monthly cost savings of 5 to 7 percent [26]. The entity page Advanced Planning and Scheduling explains the basics of capacity-constrained planning, and our guide to production scheduling software and APS goes deeper.

Keep the roles clear: classic ERP planning (MRP II) works sequentially (quantities, then dates, then capacities), often against infinite capacity. The twin does not replace the ERP system. It checks and improves its results.

7.5 Virtual commissioning

Virtual commissioning tests a machine's or line's control software against a simulation model before the physical equipment is in place. The most detailed guideline is German: VDI/VDE 3693 Part 1 (August 2016) defines virtual commissioning for process and factory automation, with the aim of finding and fixing errors from the engineering of automation systems, and describes model types and terms [14]. Part 2 (December 2018) covers introducing virtual commissioning in companies; VDI has announced a revision [15]. We found no ANSI or ISA standard dedicated to virtual commissioning unverified; US integrators typically work with these concepts and with their tool vendors' own methods.

Three coupling variants are common:

VariantControllerEquipmentUse
Model-in-the-loop (MiL)as a modelas a modelearly concept check
Software-in-the-loop (SiL)real control program on an emulated or virtual PLCas a modeltesting PLC logic without hardware
Hardware-in-the-loop (HiL)real controller hardwareas a real-time modeltesting including timing behavior and fieldbus systems

The benefit is moving troubleshooting out of the expensive on-site commissioning phase into an earlier, cheaper phase. Reliable industry-wide percentages for time savings are scarce; many published numbers are vendor claims. One documented example: at a pre-assembly line in its Saarbrücken, Germany plant, ZF, working with Fraunhofer IESE, expected to commission about 30 percent faster using a digital twin and the Eclipse BaSyx middleware; in 2021 this was an expectation, not a value measured across many projects [28]. A 2024 study by Fraunhofer IWU among machine and equipment builders in the German state of Saxony found that more than 90 percent of the companies surveyed know virtual commissioning, but only a few use its potential in practice [27].

Virtual commissioning vs. factory twin: Virtual commissioning works at the signal and control level, often in milliseconds. A factory twin works at the order and resource level, in minutes to shifts. Both can use the same layout but answer different questions. More on the entity page Virtual Commissioning.

7.6 AGV and AMR fleet planning

Automated guided vehicles (AGVs) and autonomous mobile robots (AMRs) are a textbook case for simulation, because their behavior is driven by interactions: vehicles block each other at intersections, wait at transfer stations, travel back empty and need to charge. A static calculation (transport orders per hour times average travel time) regularly underestimates the number of vehicles needed, because empty trips, waiting times and charging breaks are missing.

For safety, two US standards frame these projects. ANSI/ITSDF B56.5-2024, Safety Standard for Guided Industrial Vehicles, defines safety requirements for the design, operation and maintenance of powered, unmanned automatic guided industrial vehicles and the systems they are part of [53]. ANSI/A3 R15.08-1-2020 (R2026), Industrial Mobile Robots: Safety Requirements, Part 1, addresses manufacturers of industrial mobile robots and builds on risk assessment within a documented operating environment [54]. In Germany, the guideline VDI 2510 covers AGV systems for in-plant material flow; the current edition is from 2005, and a July 2025 draft addresses AGV and AMR systems, including vehicle types, fleet control, navigation, power supply, data transmission, infrastructure and safety [18]. A simulation does not replace the risk assessment these standards require, but it shows early where traffic rules, speed zones and mixed traffic with people create conflicts.

Typical questions for an AGV simulation:

Worked example with illustrative values: Assume an assembly area needs 60 transports per hour, and a loaded trip takes 3 minutes on average. The naive calculation gives 60 × 3 = 180 travel minutes per hour, or 3 vehicles. Add empty travel to the next pickup (also 3 minutes here) and 1 minute each for pickup and drop-off, and each transport takes 8 minutes, or 480 minutes per hour: 8 fully utilized vehicles. With a target utilization of 80 percent and 85 percent availability due to charging, you get 8 / (0.8 × 0.85) ≈ 11.8, or 12 vehicles. Congestion at intersections and waiting at transfer stations are not included yet; only simulation shows those.

The data requirement is manageable but often underestimated: you need a transport matrix (from where to where, how often, when), which can be derived from routings, bills of materials and the line-side supply concept. This is where a PPR model pays off, because it already knows the material requirements per operation. For controlling real, mixed fleets, physics-based 3D environments are increasingly used; NVIDIA, for example, describes its "Mega" blueprint (introduced as a preview in 2025) as a reference workflow for testing robot fleets in digital twins of facilities [25]. More on the entity page Automated Guided Vehicle.

Comparison of static capacity calculation and simulation.

7.7 Energy and CO2

A production twin can model energy use by state: a machine draws different amounts of power when processing, idling, setting up and stopped. Combined with the order flow, the simulation shows peak loads and the effect of measures such as moving shifts, automatic shutdown during breaks or changed sequences. The prerequisite is power values per state, which you either measure or derive from manufacturer data. Reliable figures for savings potential depend heavily on the individual case; be skeptical of blanket percentages.

7.8 Maintenance

Predictive maintenance is often cited as the prime example of a digital twin. In practice, these are two different disciplines: condition monitoring and failure prediction work with sensor data and statistical or physical damage models at the asset level. A production twin can benefit by taking predicted downtime as a scenario and showing which orders are affected and when a maintenance window does the least harm.

8. Digital twins with Microsoft Azure and Fabric

Many manufacturers run their corporate IT on Microsoft 365 and Azure. For them, the question is which Microsoft services are candidates for digital twins and what their status is. The episode Digital Twins on Azure gives an overview of Azure's role.

Azure Digital Twins

Azure Digital Twins is a platform-as-a-service (PaaS) offering for creating twin graphs based on digital models of entire environments, such as buildings, factories, energy networks or cities [21]. Models are written in the Digital Twins Definition Language (DTDL). Azure Digital Twins supports DTDL v2 and v3, and Microsoft recommends v3 because of its extended capabilities; a v3 interface can extend a v2 interface, but not the other way around [22]. Microsoft also provides ontologies that bundle DTDL models based on industry standards [22]. The overview page contained no retirement notice when we checked it [21].

Azure Digital Twins is a modeling and graph platform, not simulation software. It represents relationships and states and processes events; discrete event simulation, scenario comparison or optimization must come from other tools.

Digital twin builder in Microsoft Fabric (preview)

With digital twin builder, Microsoft introduced an item in the Real-Time Intelligence workload of Microsoft Fabric in 2025. It is used to model business concepts such as assets and processes in an ontology, map data from various source systems to instances of these entity types and create semantic relationships between them; the data lives in OneLake [23]. As of this writing, Microsoft explicitly labels digital twin builder as a preview (Microsoft Learn, page last updated May 20, 2026; checked November 20, 2026) [23]. Microsoft also points out that digital twin builder is a different service from Azure Digital Twins [21][23]. In the Fabric blog, Microsoft names manufacturing examples such as twins of machines and processes for root-cause analysis and what-if questions, as well as partners that provide manufacturing data schemas and KPI queries, for example for overall equipment effectiveness (OEE) [24].

Which service for which purpose?

NeedSuitable approachNote
Graph of assets, spaces and equipment with event processing, in productionAzure Digital Twins with DTDL v3 [21][22]generally available PaaS service; add simulation separately
Ontology over ERP, MES and sensor data on a Fabric data platformdigital twin builder in Fabric [23]preview: for pilots and evaluation; check production use against Microsoft's preview terms
Capacity, bottleneck, scenarios, layoutsimulation tool (section 15), results in Fabric or Power BIneither Azure Digital Twins nor digital twin builder is simulation software

What M365 and Azure admins contribute

A production twin is not a pure OT project. IT contributes essential building blocks:

Our guide to Azure for manufacturing covers manufacturing IT on Azure in detail.

9. Artificial intelligence and the digital twin

AI and the digital twin complement each other in both directions: the twin gives AI structured context and a safe place to experiment, and AI speeds up and extends the twin. Five patterns matter in manufacturing:

  1. Data preparation: Machine learning detects outliers in confirmations, estimates missing times and derives distributions from actual data. It is unspectacular, but often the biggest practical lever.
  2. Surrogate models: A detailed simulation model is used to "train" a neural network or another surrogate with many runs; the surrogate then delivers approximations in seconds. Useful for optimizations that need very many evaluations. The limits lie outside the trained range.
  3. Optimization and reinforcement learning: Agents learn control rules inside the simulation model, for example for sequencing or vehicle dispatching, without disturbing real production. The McKinsey metal fabrication example in section 7.3 used this approach [26]. The rules are only as good as the model's fidelity.
  4. Generative AI as the interface: Language models translate questions like "What happens if line 3 is down for a week?" into scenarios and explain results. The prerequisite is a semantically clean model (ontology, PPR graph) so the AI does not guess.
  5. Physical AI and robotics: Physics-based 3D twins serve as training and test environments for robots and autonomous vehicles; NVIDIA positions Omniverse and the Mega blueprint, based on OpenUSD, for this purpose [25].

A sober assessment: AI replaces neither validation nor domain expertise. A language model working on a faulty routing quickly produces plausible but wrong answers. The order is therefore: data foundation and model first, then AI.

10. Roadmap: implementation in six phases

The following roadmap is a guide for a production or factory twin. The durations are the author's experience for a mid-sized plant with a clearly scoped first use case unverified; McKinsey gives a range of two to three months to more than a year for twin projects, depending on team capabilities and plant complexity [26]. The post Digital twin in manufacturing: where to start also describes how to take the first step.

PhaseContentResultTypical duration
1 Questionname the decision, set metrics and targets, assign ownersone-page charter with guiding question, metrics, system boundary2–4 weeks
2 Data inventoryreview ERP, MES and layout data, check data quality, close gapsdata map, quality report, action list3–6 weeks
3 Pilot modelPPR model for one value stream or area, executable simulation modelvalidated pilot model6–12 weeks
4 Validation and first decisioncompare with actual data, run scenarios, prepare decisiondocumented decision with assumptions2–6 weeks
5 Operationalizationautomatic data feeds, roles, maintenance processes, regular schedule validationshadow in routine operation2–6 months
6 Scalingmore areas, plants, use cases, coupling with APS, energy, AGVstwin portfolio on a shared data foundationongoing

Guiding principles for the roadmap:

Help for small and mid-sized manufacturers: In the US, the NIST Manufacturing Extension Partnership (MEP), a program of the Department of Commerce's National Institute of Standards and Technology with more than 450 service locations in all 50 states and Puerto Rico, is a common starting point for smaller manufacturers that want outside support with digitalization projects [60]. NIST's ISO 23247 use-case report was written with exactly this audience in mind [47].

Waiting time rises steeply as utilization approaches 95 percent.

11. Data quality: the underrated prerequisite

In many twin projects, the first data review already shows it: the master data in the ERP system describes the plant more as it was once planned than as it works today. That is no criticism of master data management. It follows from the fact that ERP systems are maintained mainly for costing and material planning, not for simulation.

Typical data problems

Checklist before you build the model

CheckQuestionMethod
CompletenessDoes every relevant material have a routing, and every operation a work center?query for missing links
CurrencyWhen were standard times last reviewed?change date per routing
PlausibilityHow large is the gap between standard and actual times?comparison with confirmations over three to six months
GranularityAre work centers fine-grained enough for the question?cross-check with layout and a gemba walk
ConsistencyDo names match between ERP, MES and layout?mapping table
TimestampsAre confirmations booked promptly?distribution of booking times across the shift
DowntimeIs there a single downtime reason catalog?frequency analysis of reasons
OwnershipWho maintains which data, and who approves changes?RACI matrix

Rule of thumb: A simulation model may bridge data gaps with assumptions, as long as the assumptions are documented and tested in sensitivity analyses. A twin that silently calculates with wrong standard times is dangerous, because it looks precise.

A side effect many companies underestimate: the data inventory for a twin alone often improves planning quality in the ERP system, because it exposes outdated routings and wrong capacities.

12. Cost and benefit, assessed honestly

Cost drivers

In the author's assessment, the cost of a production twin is usually dominated not by software but by data and modeling work. The main cost drivers are:

For simulation studies, a German simulation services firm gives as a rule of thumb that the cost should not exceed 1 percent of the investment concerned, and refers to studies and benchmarks (including VDI) that put the cost-benefit ratio at about 1:6 on average [30]. These values come from a vendor source; check the original studies before using them in your own business case.

Documented benefit examples

Reliable, independently collected benefit figures are rare. The following values are sourced, but they are individual cases:

SourceContextValue
McKinsey (2024) [26]assembly plant, redesigned production schedule5–7% monthly cost savings through less overtime
McKinsey (2024) [26]sequence optimization at a bottleneck stationapprox. 4% lower total processing time
McKinsey (2024) [26]survey of 75 senior industrial executives (June 2022)86% consider twins applicable, 44% have already implemented one, 15% are planning to
ZF / Fraunhofer IESE (2021) [28]pre-assembly line, Saarbrücken (Germany), Eclipse BaSyx middlewareapprox. 30% faster commissioning (expectation, not an average)
Fraunhofer IWU (2024) [27]survey of machine and equipment builders in Saxony (Germany)more than 90% know virtual commissioning, only a few use its potential

For context on the US investment climate: in Deloitte's 2025 Smart Manufacturing and Operations Survey (600 executives at US manufacturers with $500 million or more in revenue, conducted August to September 2024), 78 percent of leaders said they put more than 20 percent of their improvement budget into smart manufacturing initiatives; respondents reported up to 20 percent improvement in production output [56]. These are self-reported figures for smart manufacturing as a whole, not for digital twins specifically.

The business case in five questions

  1. Which decision does the twin improve, and how often is it made (once for a capital project, or weekly in scheduling)?
  2. What does a wrong decision cost (over- or under-sized investment, late deliveries, overtime, stockouts)?
  3. How much more accurate does the decision become with the twin? A pilot gives you a first comparison between plan, simulation and actual results.
  4. What does the twin cost over three to five years, including maintenance?
  5. Which follow-on benefits arise (better master data, faster quote checks, reuse in other areas)?

For capital decisions in the millions of dollars, a single avoided mis-sizing can justify a simulation project. For ongoing planning twins, frequency of use decides.

13. Common mistakes and how to avoid them

MistakeConsequenceCountermeasure
technology before the questionexpensive platform without benefitone-page charter with a concrete decision and metric before any tool selection
confusing 3D visualization with a twinnice pictures, no answers to capacity questionsprocess logic (PPR) before geometry
modeling everything at onceproject never finishesone value stream or area as the pilot
adopting master data uncheckedprecise-looking but wrong resultsdata-quality check (section 11), comparison with actual times
no validationloss of trust at the first deviationsystematic comparison with actual data, documented assumptions
averages instead of distributionsbottlenecks and inventory underestimateddistributions from actual data, model breakdowns
a single simulation replicationa random result sold as the truthseveral replications, confidence intervals [41]
no maintenance planmodel outdated after a few monthsroles, processes and budget for maintenance
model only for specialistsknowledge leaves with one personunderstandable interfaces, training, documentation
feedback loop without approvalsafety and liability riskhuman approval, logging, IT/OT security concept
undefined termsmisunderstandings in RFP and contractspecify the integration level (model, shadow, twin) explicitly [5]

14. Standards and guidelines at a glance

Standard/guidelineTitle (short)StatusRelevance
ISO 23247-1 to -4Digital twin framework for manufacturing: overview, reference architecture, digital representation, information exchange2021 [6]framework and structure for manufacturing twins
ISO 23247-5Digital thread for digital twin2026 (listed in the ISO catalog as Edition 1, 2026-06, still shown as "under publication" on November 20, 2026) [7]linking lifecycle information
ISO 23247-6Digital twin compositionpublished July 14, 2026 [8]composing several twins
NIST AMS 400-2Use Case Scenarios for Digital Twin Implementation Based on ISO 23247May 2021 [47]US implementation guidance for ISO 23247
ISO/IEC 30173Digital twin: Concepts and terminologyNovember 2023 [9]cross-industry terms
NIST IR 8356Security and Trust Considerations for Digital Twin TechnologyFebruary 2025 [49]security and trust
IEC 63278-1Asset Administration Shell for industrial applications, Part 1: StructureDecember 14, 2023 [10]Asset Administration Shell
DIN SPEC 91345Reference Architecture Model Industrie 4.0 (RAMI 4.0)2016 [12]Industry 4.0 framework (German)
ANSI/ISA-95 (IEC 62264)Enterprise-control system integrationstandard series [58][19]levels ERP/MES/control, data models
ANSI/MTC1.4-2018 (MTConnect)manufacturing data interoperability2018 edition [57]machine data, common in US machine shops
IEC 62541 (OPC UA)OPC Unified Architecturestandard seriesmachine communication and information models
VDI 3633 Part 1Simulation of systems in materials handling, logistics and production: fundamentalsDecember 2014 [13]method of the simulation study (German)
VDI/VDE 3693 Part 1Virtual commissioning: model types and glossaryAugust 2016 [14]virtual commissioning terms (German)
VDI/VDE 3693 Part 2Virtual commissioning: introduction in companiesDecember 2018, revision announced [15]introducing virtual commissioning (German)
VDI 4499 Part 1Digital factory: fundamentalsnew edition April 2026 (first edition February 2008) [16]term and architecture of the digital factory (German)
ANSI/ITSDF B56.5-2024Safety Standard for Guided Industrial Vehicles2024 [53]AGV safety (US)
ANSI/A3 R15.08-1-2020 (R2026)Industrial Mobile Robots: Safety Requirements, Part 1reaffirmed 2026 [54]AMR safety (US)
VDI 2510Automated guided vehicle systems (AGVS)October 2005, draft July 2025 [18]AGVs and AMRs (German)
ISA/IEC 62443Security for industrial automation and control systemsstandard series [59]security of automation systems
NIST SP 800-82 Rev. 3Guide to Operational Technology (OT) SecuritySeptember 2023 [55]OT security guidance (US)

15. Software categories: a neutral comparison

The market is hard to navigate because many vendors call their product a "digital twin". A classification by function is more helpful:

CategoryCore functionStrengthsLimitsTypical users
Discrete event simulation toolsmaterial flow and factory simulationhigh modeling freedom, established methodmodel building is effortful, needs expertisesimulation experts, factory planning
Multi-method simulation toolscombination of discrete event, agent-based, system dynamicsflexible for mixed questionssteep learning curvesimulation and logistics experts
Digital factory and PLM suiteslayout, robotics, process planning, simulation in a PLM contextcontinuity from design to productioncomplexity, license costlarge enterprises, automotive
Virtual commissioning toolsequipment models with PLC coupling (SiL/HiL)control testing before installationfocus on equipment, not the plantcontrols engineers, machine builders
Value stream and PPR-based planning toolsmodel from ERP and value stream data, simulation, scenariosfast build from existing data, close to operationsless suited to detailed conveyor systemsproduction planning, lean, plant management
APS systemscapacity-constrained planning and sequencingoperational schedulingsimulation often limitedproduction planning and control
IoT and twin platformsasset models, event processing, graphs (e.g., Azure Digital Twins)scale, integration, real timeno simulation out of the boxIT, data platform teams
3D and physics platformsphotorealistic scenes, physics, robot training (e.g., on OpenUSD)visualization, robotics, AI trainingprocess logic and order dynamics not the focusrobotics, large projects

Selection criteria: Does the tool fit the question and level of detail? How fast can a model be built from your existing data? Can operations staff use it themselves? How is it maintained? Which interfaces to ERP, MES and your data platform exist? Which standards (AAS, OPC UA, MTConnect, DTDL) are supported? Where does the data reside, and who has access?

16. Security, data ownership and regulation

A production twin holds sensitive information: product structures, process times, capacities and customer orders describe a company's know-how and competitive position. The higher the integration level, the greater the risk.

17. Building a twin from ERP and value stream data with iFAKT Polaris

Note: The author works at iFAKT GmbH.

This section describes one solution approach that follows the principle explained in section 5: building the production twin from existing ERP and value stream data through a product-process-resource model. The information comes from iFAKT GmbH's product pages and can be checked there; the author has no independent comparative tests.

iFAKT GmbH, headquartered in Stuttgart, Germany, says it has been active for more than 25 years and develops software for value stream mapping, production simulation, planning and optimization [35]. The company describes its platform iFAKT Polaris as a way to connect ERP data with a digital twin of production in order to optimize plans and expose bottlenecks; the platform includes modules for value stream and swimlane modeling (VSM/BSM), Designer, Simulator, Optimizer, Operator and Analyzer [35].

Polaris Designer: According to the vendor's page, Designer turns input data into a structured PPR knowledge graph that connects products (manufacturing and engineering bills of materials, MBOM/EBOM), processes (setup, machine and handling times) and resources (stations, teams, zones) with their constraints in one model. The inputs are ERP data, manufacturing BOMs, process times, resource structures and constraints. From these, Designer automatically generates network diagrams based on the real production logic, shows the critical path and critical resources, highlights bottleneck processes, compares current and optimized lead times and assigns zones based on product-process relationships. The vendor positions the graph as the common basis ("single source of truth") for simulation and optimization [33]. More on the entity page Polaris Designer.

Comparison of virtual and physical commissioning.

Polaris Simulator: According to the vendor, Simulator builds on the PPR graph created in Designer and runs the network diagrams through configurable station, line and shop-floor (hall) models, for single and multiple lines. It is meant to make capacity utilization across shifts and scenarios transparent, detect bottlenecks and utilization imbalances over time, show over- and under-utilization as well as time-based labor utilization, and evaluate scenarios for capacity, labor deployment and buffers as well as dynamic product mixes on shared resources [34]. More on the entity page Polaris Simulator.

Technical background: iFAKT employees have published on the underlying questions in the German trade literature, for example on dynamic simulation of value streams (ZWF 109(11), 2014) [31] and, with research partners, on a universal data interface for digital value stream services (ZWF 118(5), 2023) [32].

Assessment: A PPR- and value-stream-based approach is particularly suited to questions of production planning, capacity, bottlenecks and labor deployment in high-mix assembly and fabrication areas. For detailed conveyor systems, robot cells or virtual commissioning at the signal level, the specialized categories in section 15 are a better fit. As with any tool, test in a pilot with your own data whether the results answer your question. Our dedicated guide to iFAKT Polaris covers the platform in more depth.

18. Glossary

TermExplanation
Advanced planning and scheduling (APS)software for capacity-constrained planning and sequencing
Agent-based simulation (ABS)modeling of autonomous units (agents) with their own rules, whose interaction produces system behavior
AGV / AMRautomated guided vehicle / autonomous mobile robot [53][54]
Asset Administration Shell (AAS)standardized digital representation of an asset according to IEC 63278 [10]
Bottleneck (constraint)resource that limits the throughput of the overall system [39]
Digital factoryumbrella term for digital models, methods and tools for planning and improving the real factory (German guideline VDI 4499) [16][17]
Digital modeldigital representation without automatic data exchange with the physical object [5]
Digital shadowrepresentation with automatic data flow from physical to digital, but manual flow back [5]
Digital threadconnected linking of information across the lifecycle; addressed in ISO 23247-5 [7]
Digital twinrepresentation with automatic data flow in both directions [5]; often used more broadly in practice
Discrete event simulation (DES)simulation whose clock jumps from event to event; the standard in production simulation
DTDLDigital Twins Definition Language, JSON-based modeling language for Azure Digital Twins [22]
ERPenterprise resource planning, the core business system with master data, orders and material planning
HiL / SiL / MiLhardware-, software-, model-in-the-loop: coupling variants for virtual commissioning
ISA-95 / IEC 62264standard series for integrating enterprise and control systems [58]
Little's LawL = λ · W: average inventory equals throughput rate times lead time in steady state [37]
Material flow simulationsimulation of material and order flows through production and logistics, usually discrete event
MBOM / EBOMmanufacturing bill of materials / engineering bill of materials
MESmanufacturing execution system, operations management at ISA-95 level 3
MTConnectopen standard for manufacturing data interoperability, published as ANSI/MTC1.4-2018 [57]
OPC UAvendor-independent communication standard with information models (IEC 62541)
PPR modelproduct-process-resource model, the structuring principle of the digital factory
Replicationrepeated simulation run with different random numbers for statistical confidence [41]
Validationchecking whether a model represents reality accurately enough for its purpose
Value stream simulationdynamic simulation of a value stream map over time [31]
Verificationchecking whether a model has been implemented correctly
Virtual commissioningtesting control software against a simulation model before physical commissioning [14]
VVUQverification, validation and uncertainty quantification; proposed by NIST as a future ISO 23247 part [48]
Warm-up periodinitial phase of a simulation run whose results are discarded because of the empty starting state

19. FAQ: digital twins in manufacturing

What is a digital twin in manufacturing, in simple terms?

A digital twin is an executable computer model of your production that is updated with data from real operations. You can use it to play through operations, find bottlenecks and test changes before you make them on the real shop floor.

What are the 4 types of digital twins?

A common four-level scheme distinguishes component (part) twins, asset twins, system (unit) twins and process twins [52]. For manufacturing decisions, a more useful split is product, process, asset, factory, performance and supply chain twins (see section 3). None of these classifications is standardized; ISO/IEC 30173 describes twin types only at a general level [9].

What is the difference between a digital twin and a digital shadow?

According to Kritzinger et al., in a digital shadow data flows automatically from the physical to the digital object, but the return path is manual. In a digital twin, data flows automatically in both directions [5]. A digital model has no automatic data exchange at all.

What are examples of digital twins in manufacturing?

Typical examples are a factory model that compares layout variants before a new building is approved, a simulation fed daily from ERP and MES that checks whether this week's schedule holds, a virtual commissioning model that tests PLC code before a line is installed, and an AGV fleet model that sizes vehicles and charging. McKinsey documents cases such as a redesigned assembly schedule with 5 to 7 percent monthly cost savings and a bottleneck sequence that cut processing time by about four percent [26].

What is the difference between a digital twin and a simulation?

A simulation is a model you run experiments with. It becomes a digital shadow or twin when it is fed automatically with operating data and its results flow back into decisions or controls. Many twins contain a simulation at their core.

Is a 3D model or a BIM model a digital twin?

Not on its own. A 3D scan, CAD layout or building information model (BIM) captures geometry. Without process logic (routings, times, resources) and a data connection to operations, it cannot answer capacity or lead-time questions. It can be a useful layer of a twin, especially in brownfield layout planning.

What is the difference between production simulation and virtual commissioning?

Production simulation evaluates operations at the order and resource level (throughput, lead time, bottlenecks). Virtual commissioning tests a machine's control software at the signal level against an equipment model before the physical equipment is built [14].

What data does a manufacturing digital twin need?

For a production and factory twin, you mainly need bills of materials, routings with times, work centers and capacities, shift patterns, orders and confirmations. This data comes mostly from ERP and MES. Machine and sensor data improves the model but is rarely the starting point.

Can you build a digital twin from ERP data?

Yes. For questions of capacity, lead time and scheduling, the ERP system is the most important source. It holds product, process and resource data in structured form. A data-quality check is essential, because standard and setup times often deviate from reality.

What type of simulation is used in manufacturing?

Mostly discrete event simulation, whose clock jumps from event to event. System dynamics is added for strategic questions, agent-based simulation for vehicles and people, and physics-based 3D simulation for robot cells and control testing.

Main standards for manufacturing digital twins.

How accurate does a digital twin need to be?

Accurate enough for the decision it supports, and no more. Validate the model against actual data for the metrics that matter (for example throughput or lead time), document assumptions and run sensitivity analyses. NIST is working on a verification, validation and uncertainty quantification framework for manufacturing twins [48].

What standards apply to digital twins in manufacturing?

The core standards are ISO 23247 (digital twin framework for manufacturing, Parts 1 to 6) [6][7][8], ISO/IEC 30173 (terminology) [9], IEC 63278-1 (Asset Administration Shell) [10] and ISA-95 / IEC 62264 [58]. For security, use ISA/IEC 62443 [59] and NIST SP 800-82 [55]. NIST AMS 400-2 shows how to apply ISO 23247 [47]. German guidelines (VDI 3633 for simulation, VDI/VDE 3693 for virtual commissioning, VDI 4499 for the digital factory) add method detail [13][14][16].

Are digital twins a good fit for small and mid-sized manufacturers?

Yes, if you start with a clearly scoped question. A pilot for one value stream or area based on existing ERP data takes far less effort than a plant-wide IoT project and delivers verifiable benefit sooner. NIST's ISO 23247 use-case report targets exactly this group [47], and NIST MEP centers offer outside support [60].

How much does a digital twin cost?

That depends on scope, data situation and integration level. The largest cost items are usually data preparation, modeling, validation and maintenance, not the software. A German simulation services firm gives a rule of thumb of at most 1 percent of the investment concerned for simulation studies [30].

How long does implementation take?

McKinsey gives a range of two to three months to more than a year for twin projects, depending on team capabilities and plant complexity [26]. A pilot focused on one concrete decision is usually possible within a few months.

How does a digital twin help plan AGV and AMR fleets?

It simulates vehicles with trips, empty travel, waiting times, intersection conflicts and charging breaks. That way you determine the number of vehicles, routes and charging strategy, which a static calculation regularly underestimates.

What role does artificial intelligence play?

AI helps prepare data, speeds up simulations through surrogate models, learns control rules inside the model and makes twins usable through natural language. It requires a validated model and clean data.

Is Azure Digital Twins the same as digital twin builder in Fabric?

No. Microsoft explicitly states that these are different services [21][23]. Azure Digital Twins is a PaaS service for twin graphs with DTDL; digital twin builder is an ontology and mapping tool in Microsoft Fabric and is in preview as of this writing [23].

Who invented the digital twin?

The concept goes back to Michael Grieves, who presented it in 2002 in the context of product lifecycle management; Grieves credits the name "digital twin" to John Vickers of NASA [1][2]. Other authors point to earlier precursors, for example in research on virtual manufacturing [4].

20. Conclusion

The digital twin in manufacturing is less a new technology than the consistent combination of three proven building blocks: a structured model of products, processes and resources; a simulation that captures dynamics and variability; and a data feed from real operations. The standards exist, from ISO 23247 and ISA-95 to the Asset Administration Shell, NIST provides US implementation guidance, and the method of factory simulation has been tested for decades.

The most common mistake is not the wrong technology but a missing purpose. Start with a decision that today rests too often on gut feeling or a spreadsheet: a capital investment, a new product mix, an AGV fleet, a weekly schedule that regularly does not hold. Check your ERP data honestly, build a validated pilot model and then decide which integration level the next step justifies. That is how you get a twin that does not just look good but improves decisions.

Further reading on m365.fm

Blog posts and episodes

Entity pages

Related guides

Go deeper: related articles

Note: The author works at iFAKT GmbH.

Sources

All online sources were retrieved on November 20, 2026.

  1. Grieves, M.; Vickers, J. (2017): Digital Twin: Mitigating Unpredictable, Undesirable Emergent Behavior in Complex Systems. In: Kahlen, F.-J.; Flumerfelt, S.; Alves, A. (eds.): Transdisciplinary Perspectives on Complex Systems. Springer, Cham. DOI: 10.1007/978-3-319-38756-7_4
  2. Grieves, M.: Digital and Physical Twins (book chapter, provided in the ASME resource library). https://event.asme.org/Events/media/library/resources/digital-twin/Digital-and-Physical-Twins.pdf
  3. Glaessgen, E. H.; Stargel, D. S. (2012): The Digital Twin Paradigm for Future NASA and U.S. Air Force Vehicles. 53rd AIAA/ASME/ASCE/AHS/ASC Structures, Structural Dynamics and Materials Conference, Honolulu, April 23–26, 2012. NASA Technical Reports Server 20120008178. https://ntrs.nasa.gov/citations/20120008178
  4. Zhou, J.; Zhang, S.; Gu, M. (2022): Revisiting Digital Twins: Origins, Fundamentals and Practices. arXiv:2203.12867 (with reference to Shafto et al. 2010, NASA Modeling, Simulation, Information Technology & Processing Roadmap). https://arxiv.org/abs/2203.12867
  5. Kritzinger, W.; Karner, M.; Traar, G.; Henjes, J.; Sihn, W. (2018): Digital Twin in manufacturing: A categorical literature review and classification. IFAC-PapersOnLine 51(11), pp. 1016–1022. DOI: 10.1016/j.ifacol.2018.08.474
  6. ISO 23247-1:2021 Automation systems and integration: Digital twin framework for manufacturing, Part 1: Overview and general principles (Parts 2 to 4 also 2021). Catalog entry: https://iteh.eu/catalog/standards/iso/7df6fef2-6487-43da-9a48-eaba332a9ffc/iso-23247-1-2021
  7. ISO 23247-5 Automation systems and integration: Digital twin framework for manufacturing, Part 5: Digital thread for digital twin (Edition 1, 2026-06; status "under publication" when checked on November 20, 2026). https://www.iso.org/standard/87425.html
  8. ISO 23247-6:2026 Automation systems and integration: Digital twin framework for manufacturing, Part 6: Digital twin composition (published July 14, 2026, stage 60.60). https://committee.iso.org/standard/87426.html
  9. ISO/IEC 30173:2023 Digital twin: Concepts and terminology (November 2023). https://www.iso.org/standard/81442.html
  10. IEC 63278-1:2023 Asset Administration Shell for industrial applications, Part 1: Asset Administration Shell structure (December 14, 2023). https://webstore.iec.ch/en/publication/65628
  11. ZVEI (2020): User organization Industrial Digital Twin Association founded (founded September 24, 2020). https://www.zvei.org/en/press-media/pressarea/user-organization-industrial-digital-twin-association-founded
  12. DIN SPEC 91345:2016-04 Reference Architecture Model Industrie 4.0 (RAMI4.0). https://www.dinmedia.de/de/technische-regel/din-spec-91345/250940128
  13. VDI 3633 Part 1:2014-12 Simulation of systems in materials handling, logistics and production: Fundamentals. https://vdi.de/richtlinien/details/vdi-3633-blatt-1-simulation-of-systems-in-materials-handling-logistics-and-production-fundamentals ; VDI 3633 Part 8 (machine-oriented simulation, 3D motion and process simulation): https://www.vdi.de/mitgliedschaft/vdi-richtlinien/details/vdi-3633-blatt-8-simulation-of-systems-in-materials-handling-logistics-and-production-machine-oriented-simulation-3d-motion-and-process-simulation
  14. VDI/VDE 3693 Part 1:2016-08 Virtual commissioning: Model types and glossary. https://vdi.de/richtlinien/details/vdivde-3693-blatt-1-virtual-commissioning-model-types-and-glossary
  15. VDI/VDE 3693 Part 2:2018-12 Virtual commissioning: Introduction of virtual commissioning in companies; revision announced. https://vdi.de/en/home/vdi-standards/details/vdivde-3693-blatt-2-virtual-commissioning-introduction-of-virtual-commissioning-in-companies ; edition history: https://dinmedia.de/en/draft-technical-rule/vdi-vde-3693-blatt-2/276110751
  16. VDI 4499 Part 1:2026-04 Digital factory: Fundamentals. https://vdi.de/richtlinien/details/vdi-4499-blatt-1-digital-factory-fundamentals
  17. University of Duisburg-Essen, Chair VIP: lecture notes "Digitale Fabrik" (quotes the definition from VDI 4499 Part 1:2008; in German). https://www.uni-due.de/imperia/md/content/vip/scriptum_digitalefabrik.pdf
  18. VDI 2510:2005-10 Automated guided vehicle systems (AGVS). https://vdi.de/richtlinien/details/vdi-2510-automated-guided-vehicle-systems-agvs ; draft VDI 2510:2025-07: https://www.dinmedia.de/de/technische-regel-entwurf/vdi-2510/388587666
  19. OPC Foundation: OPC 10030 ISA-95 Common Object Model, section 4.2.3 ISA-95. https://reference.opcfoundation.org/specs/OPC-10030/4.2.3
  20. Schuh, G.; Anderl, R.; Dumitrescu, R.; Krüger, A.; ten Hompel, M. (2020): Industrie 4.0 Maturity Index. Managing the Digital Transformation of Companies. Update 2020 (acatech STUDY). https://en.acatech.de/publication/industrie-4-0-maturity-index-update-2020/
  21. Microsoft Learn: What is Azure Digital Twins? https://learn.microsoft.com/azure/digital-twins/overview
  22. Microsoft Learn: Learn about twin models and how to define them in Azure Digital Twins (DTDL v2 and v3). https://learn.microsoft.com/en-ca/azure/digital-twins/concepts-models
  23. Microsoft Learn: What Is Digital Twin Builder (Preview)? (last updated May 20, 2026; preview label re-checked November 20, 2026). https://learn.microsoft.com/en-us/fabric/real-time-intelligence/digital-twin-builder/overview
  24. Microsoft Fabric Blog: Digital twin builder in Microsoft Fabric Real-Time Intelligence. https://blog.fabric.microsoft.com/en-us/blog/digital-twin-builder-in-microsoft-fabric-real-time-intelligence-revolutionizing-digital-twin-creation-and-management
  25. NVIDIA Blog (March 31, 2025): Industrial Ecosystem Adopts Mega NVIDIA Omniverse Blueprint to Train Physical AI in Digital Twins. https://blogs.nvidia.com/blog/mega-omniverse-blueprint-industrial-digital-twins/
  26. Camarella, S.; Conway, M. P.; Goering, K.; Huntington, M. (2024): Digital twins: The next frontier of factory optimization. McKinsey & Company, January 10, 2024. https://www.mckinsey.com/capabilities/operations/our-insights/digital-twins-the-next-frontier-of-factory-optimization
  27. Fraunhofer IWU (2024): Sächsische Maschinenbauer nutzen Vorteile der Virtuellen Inbetriebnahme oft noch nicht (press release on the SaxoVI study, August 13, 2024; in German). https://www.iwu.fraunhofer.de/content/dam/iwu/de/documents/Presse/2024-Saechsische-Maschinenbauer-nutzen-Vorteile-der-Virtuellen-Inbetriebnahme-oft-noch-nicht.pdf
  28. Poll, D. (2021): Digitalisierung bei ZF: Neue Methode spart 30 Prozent Zeit. produktion.de, June 16, 2021 (in German). https://www.produktion.de/technik/digitalisierung-bei-zf-neue-methode-spart-30-prozent-zeit/1656151
  29. Fraunhofer IESE: Digitaler Zwilling in der Produktion & Industrie 4.0 (in German). https://www.iese.fraunhofer.de/de/leistungen/digitaler-zwilling.html
  30. SimPlan AG: FAQ Simulation (definition according to VDI 3633, cost-benefit rules of thumb). https://www.simplan.de/en/knowledge/faq-simulation-en
  31. Türck, S.; Weimer, A.; Schubert, L.; Drees, J. (2014): Dynamische Simulation von Wertströmen [Dynamic simulation of value streams]. Zeitschrift für wirtschaftlichen Fabrikbetrieb (ZWF) 109(11), pp. 839–842. DOI: 10.3139/104.111242
  32. Böhm, M.; Drees, J.; Sai, B.; Erlach, K.; Stambera, S.; Teriete, T. (2023): Universelle Datenschnittstelle für digitale Wertstromdienste [Universal data interface for digital value stream services]. ZWF 118(5), pp. 293–297. DOI: 10.1515/zwf-2023-1062
  33. iFAKT GmbH: Polaris Designer (product page). https://www.ifakt.de/en/solutions/designer
  34. iFAKT GmbH: Polaris Simulator (product page). https://www.ifakt.de/en/solutions/simulator
  35. iFAKT GmbH: home page (company and Polaris platform). https://www.ifakt.de/
  36. European Commission: Cyber Resilience Act, summary (Regulation (EU) 2024/2847). https://digital-strategy.ec.europa.eu/en/policies/cra-summary
  37. Little, J. D. C. (1961): A Proof for the Queuing Formula: L = λW. Operations Research 9(3), pp. 383–387. DOI: 10.1287/opre.9.3.383
  38. Forrester, J. W. (1961): Industrial Dynamics. MIT Press, Cambridge, MA.
  39. Goldratt, E. M.; Cox, J. (1984): The Goal: A Process of Ongoing Improvement. North River Press.
  40. Rother, M.; Shook, J. (1998): Learning to See: Value Stream Mapping to Add Value and Eliminate Muda. Lean Enterprise Institute, Brookline, MA.
  41. Law, A. M. (2015): Simulation Modeling and Analysis. 5th ed., McGraw-Hill Education, New York.
  42. SYMESTIC: Was ist ISA-95? (level model, relation to IEC 62264; in German). https://www.symestic.com/de-de/was-ist/isa-95
  43. Umbrex: ISO 23247 Digital Twin Framework for Manufacturing (overview of parts and reference architecture). https://umbrex.com/resources/frameworks/manufacturing-industrial-equipment-frameworks/iso-23247-digital-twin-framework-for-manufacturing/
  44. Kingman, J. F. C. (1961): The single server queue in heavy traffic. Mathematical Proceedings of the Cambridge Philosophical Society 57(4), pp. 902 ff. DOI: 10.1017/S0305004100036094
  45. Shao, G. (2021): Use Case Scenarios for Digital Twin Implementation Based on ISO 23247. NIST Advanced Manufacturing Series (NIST AMS) 400-2, May 4, 2021. DOI: 10.6028/NIST.AMS.400-2; publication page: https://www.nist.gov/publications/use-case-scenarios-digital-twin-implementation-based-iso-23247
  46. NIST: Digital Twins for Advanced Manufacturing (project page; ISO 23247 Part 5 reference implementation, proposed VVUQ framework as Part 7, MTConnect interface, NIST Digital Twin Testbed). https://nist.gov/programs-projects/digital-twins-advanced-manufacturing
  47. Voas, J.; Mell, P.; Laplante, P.; Piroumian, V. (2025): Security and Trust Considerations for Digital Twin Technology. NIST IR 8356 (final), February 14, 2025 (initial public draft 2021 titled "Considerations for Digital Twin Technology and Emerging Standards"). DOI: 10.6028/NIST.IR.8356; https://csrc.nist.gov/pubs/ir/8356/final
  48. National Academies of Sciences, Engineering, and Medicine (2024): Foundational Research Gaps and Future Directions for Digital Twins. Consensus Study Report, The National Academies Press, Washington, DC (definition and quotes on p. 22). https://www.nationalacademies.org/our-work/foundational-research-gaps-and-future-directions-for-digital-twins ; chapter: https://www.nationalacademies.org/read/26894/chapter/4
  49. Digital Twin Consortium (2020): Digital Twin Consortium Defines Digital Twin (definition released December 3, 2020). https://www.digitaltwinconsortium.org/2020/12/digital-twin-consortium-defines-digital-twin ; current definition page: https://www.digitaltwinconsortium.org/initiatives/the-definition-of-a-digital-twin/
  50. IBM: What Is a Digital Twin? (component, asset, system and process twins). https://www.ibm.com/think/topics/what-is-a-digital-twin
  51. ANSI/ITSDF B56.5-2024: Safety Standard for Guided Industrial Vehicles. ANSI Blog summary: https://blog.ansi.org/ansi/ansi-itsdf-b56-5-2024-guided-industrial-vehicles/
  52. ANSI/A3 R15.08-1-2020 (R2026): Industrial Mobile Robots, Safety Requirements, Part 1: Requirements for the Industrial Mobile Robot (reaffirmed 2026, no technical changes). ANSI Webstore: https://webstore.ansi.org/standards/ria/ansia3r15082020r2026
  53. Stouffer, K. et al. (2023): Guide to Operational Technology (OT) Security. NIST SP 800-82 Rev. 3, September 28, 2023. DOI: 10.6028/NIST.SP.800-82r3; https://csrc.nist.gov/pubs/sp/800/82/r3/final
  54. Deloitte (2025): 2025 Smart Manufacturing and Operations Survey, press release May 1, 2025 (600 executives, US manufacturers with $500 million+ revenue, survey August–September 2024). https://www.deloitte.com/us/en/about/press-room/deloitte-2025-smart-manufacturing-survey.html
  55. MTConnect Institute: MTConnect Standard, ANSI/MTC1.4-2018, Part 1.0 Overview and Fundamentals, Version 1.4.0. https://docs.mtconnect.org/ANSI_MTC1_4-2018.pdf ; about MTConnect: https://www.mtconnect.org/about
  56. International Society of Automation (ISA): ISA-95 Standard: Enterprise-Control System Integration (ANSI/ISA-95, IEC 62264). https://www.isa.org/standards-and-publications/isa-standards/isa-95-standard
  57. International Society of Automation (ISA): ISA/IEC 62443 Series of Standards. https://www.isa.org/standards-and-publications/isa-standards/isa-iec-62443-series-of-standards
  58. NIST: Manufacturing Extension Partnership (MEP). https://www.nist.gov/mep
  59. Federal Trade Commission: Guides Concerning the Use of Endorsements and Testimonials in Advertising, 16 CFR Part 255, § 255.5 (disclosure of material connections, including an employee example); FTC notice on the revised Guides. https://www.ftc.gov/system/files/ftc_gov/pdf/P204500%20Guides%20Concerning%20Endors%20and%20Testimonials.pdf